Claim No: CA-007-2017
IN THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS
IN THE COURT OF APPEAL
BETWEEN:
DAS REAL ESTATE OWNED AND REPRESENTED BY MUSSABEH SALEM MUSSABEH HUMAID ALMUHAIRI
Claimant/Appellant
and
FIRST ABU DHABI BANK PJSC
(FORMERLY NATIONAL BANK OF ABU DHABI PJSC)
Defendant/Respondent
AMENDED ORDER OF DEPUTY REGISTRAR NOUR HINEIDI
UPON the Defendant’s Notice of Commencement of Assessment of Bill of Costs dated 3 February 2019 (the “Application”)
AND UPON reviewing the Claimant’s Points of Dispute dated 27 February 2019 (“Points of Dispute”)
AND UPON reviewing the Defendant’s Response to the Claimant’s Points of Dispute dated 17 March 2019 (the “Response”)
UPON reading the Judgment of the Court of Appeal in CA-007-2017 issued on 12 April 2018
AND UPON reading the Judgment of Deputy Chief Justice Sir David Steel in CFI-002-2016 issued on 10 August 2017
AND UPON reading the Order of H.E. Justice Shamlan Al Sawalehi issued on 4 October 2016 (the “First Costs Order”)
AND UPON reading the Order of Justice Sir David Steel issued on 8 February 2016
AND UPON considering all other relevant material on the case file
IT IS HEREBY ORDERED THAT:
- The Claimant shall pay the Defendant’s legal costs (including disbursements) in CFI-002-2016 and CA-007-2017 assessed in the total amount of AED 4,415,188 (“Costs”).
- The Claimant shall pay the Defendant’s Costs within 30 days from the date of this Order
Issued by:
Nour Hineidi
Date of Issue: 25 August 2019
At: 4.30pm