Claim No: CFI 070/2018
THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS
IN THE COURT OF FIRST INSTANCE
BETWEEN
IDBI BANK LIMITED
Claimant
And
(1) MABANI DELMA GENERAL CONTRACTING CO LLC
(2) HELIOPOLIS ELECTRIC COMPANY LLC
(3) DELMA ENGINEERING PROJECTS COMPANY LLC
(4) DELMA EMIRATES DIESEL
(5) DELMA EMIRATES GENERAL TRANSPORT
(6) AHMED KHALIL KHALED ALMERAIKHI
(7) SHERIFA AHMED KHALIL KHALED ALMERAIKHI
(8) MARIAM AHMED KHALED ALMERAIKHI
Defendants
CONSENT ORDER
UPON the agreement of the First, Third, Fourth, Fifth, Sixth, Seventh and Eighth Defendant (“Applicants”) and the Claimant.
IT IS ORDERED BY CONSENT THAT:
1. The Claimant shall serve its evidence in answer to the evidence included in the Application for an order setting aside the order for judgment in default, made by judicial officer Maha Al Mehairi on 23 October 2019, by 1 June 2020.
2. Costs in the case.
Issued by:
Nour Hineidi
Deputy Registrar
Date of Issue: 19 May 2020
At: 3pm