Quantcast
Channel: DIFC Courts
Viewing all 1139 articles
Browse latest View live

CFI 020/2015 Mohammad Bin Hamad Bin Abdul Karim Al Mojil & another v Protiviti Member Firm (Middle East) Limited

$
0
0

Claim No: CFI-020-2015

THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS

 

IN THE COURT OF FIRST INSTANCE

BETWEEN

(1) MOHAMMAD BIN HAMAD ABDUL-KARIM AL-MOJIL

(2) ADEL BIN MOHAMMAD BIN HAMAD AL-MOJIL

                                                                                          Claimants

and

PROTIVITI MEMBER FIRM (MIDDLE EAST) LIMITED

Defendant


ORDER OF JUDICIAL OFFICER MAHA AL MEHAIRI


UPON reviewing the Claimants’ Application Notice CFI 020-2015/5 dated 31 January 2017 seeking the disclosure of documents (the “Application”)

AND UPON reading the correspondence between the parties and the Court referred to in the Application

AND UPON reading the relevant material in the case file

IT IS HEREBY ORDERED THAT:

1.The Application is granted.

2. The Defendant shall produce to the Claimants, by no later than 2pm on Tuesday, 7 February 2017, the Report dated 30 June 2013 which the Defendant prepared for the Capital Markets Authority of the Kingdom of Saudi Arabia (including any appendices thereto) as referred to in paragraph 7 of the Defendant’s Summary of its Defence and elsewhere in the Defendant’s Statement of Defence dated 19 December 2016.

3. The costs in relation to the Application shall be costs in the case.

 

Issued by:

Natasha Bakirci

Assistant Registrar

Date of issue: 5 February 2017

At: 4pm

The post CFI 020/2015 Mohammad Bin Hamad Bin Abdul Karim Al Mojil & another v Protiviti Member Firm (Middle East) Limited appeared first on DIFC Courts.


Haley LLC v Hakon [2016] SCT 199

$
0
0

laim No: SCT 199/2016

THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS 

In the name of His Highness Sheikh Mohammad Bin Rashid Al Maktoum, Ruler of Dubai 

IN THE SMALL CLAIMS TRIBUNAL OF DIFC COURTS

BEFORE SCT JUDGE MAHA AL MEHAIRI 

BETWEEN 

HALEY LLC

 Claimant 

and

 

HAKON 

Defendant 

 

Hearing:         3 January 2017

Judgment:     30 January 2017


JUDGMENT OF SCT JUDGE MAHA AL MEHAIRI


UPON the Claim Form being filed on 16 November 2016;

AND UPON the Defendant filing an application to contest jurisdiction on 23 November 2016;

AND UPON a Jurisdiction Hearing being held before SCT Judge Mariam Deen on 28 November, with the Claimant in attendance but the Defendant failing to attend despite receiving sufficient notice of the Hearing;

AND UPON an Order being issued by SCT Judge Mariam Deen on 28 November 2016 finding the Small Claims Tribunal of the DIFC Courts to have jurisdiction to hear the dispute;

AND UPON the parties being called on 5 December 2016 for a Consultation and 12 December 2016 for a Second Consultation with SCT Officer Ayesha Bin Kalban, with the Claimant’s representative and the Defendant in attendance;

AND UPON the parties not having reached settlement;

AND UPON a Hearing having been scheduled before SCT Judge Mariam Deen on 21 December 2016, with the Claimant’s representative in attendance and the Defendant participating via telephone;

AND UPON a Second Hearing having been scheduled before SCT Judge Maha Al Mehairi on 3 January 2016, with the Claimant’s representative in attendance and the Defendant attending by phone;

AND UPON reviewing all documents and evidence submitted in the Court file;

IT IS HEREBY ORDERED THAT:

1.The Defendant shall pay the Claimant the amount AED 50,030.56 being the service charge for the Defendant’s Property.

2. The Defendant shall reimburse the Claimant for the Court fee in the sum of AED 2,382.

Issued by:

Maha AlMehairi

SCT Judge

Date of issue: 30 January 2017

At: 12pm

THE REASONS

Parties

1.Haley (hereafter the “Claimant”) is a legal entity filing a claim against the Defendant regarding the alleged non-payment of service charges.

2. Hakon (hereafter the “Defendant”) is the owner of Unit, DIFC, Dubai, UAE (the “Property”).

Background and the Preceding History

3. On 16 November 2016 the Claimant filed a claim in the DIFC Courts’ Small Claims Tribunal (the “SCT”) seeking payment by the Defendant of service charges and penalties amounting to AED 50,030.58, relating to the Defendant’s ownership of the Property. The Claimant also sought reimbursement of the Court fee.

4. The Defendant responded to the claim on 23 November 2016 by contesting the jurisdiction of the DIFC Courts and the Small Claims Tribunal over the dispute. A Jurisdiction Hearing was held before SCT Judge Mariam Deen on 28 November with the Claimant’s representative’s oral submissions being heard and the Defendant’s written submissions being considered due to his failure to attend despite receiving sufficient notice of the Hearing. SCT Judge Mariam Deen issued an Order on 28 November 2016 finding the Small Claims Tribunal of the DIFC Courts to have jurisdiction to hear the dispute.

5. The parties were called for a Consultation with SCT Officer Ayesha Bin Kalban on 5 December 2016, and a Second Consultation on 12 December 2016, with the Claimant’s representative and the Defendant in attendance, however, a settlement could not be reached.

6. A Hearing was scheduled before SCT Judge Mariam Deen on 21 December 2016, with the Claimant’s representative attending in person and the Defendant attending via telephone, although due to sickness, the Defendant was unable to give significant oral submissions. Both parties were allowed additional time to make further written submissions and a Second Hearing was scheduled before me on 3 January 2016. 

The Claim

7. The Claimant argues that, on 7 October 2013, pursuant to Strata Title Law (DIFC Law No. 5 of 2007), Haley was established to manage the building Haley LLC, DIFC and this entity is therefore responsible for invoicing all unit owners to pay service charges in order to manage the building.

8. The dispute arising between the parties is in regards to the Defendant’s alleged failure to pay the service charge in relation to the residential in DIFC. The Claimant contends that the Defendant, despite a number of follow-ups and letters, has failed to pay the service charges totalling an amount of AED 50,030.56 which comprises as follows: (the “Service Charge”)

(a) Service charges in the amount of AED 49,109.

(b) Penalty for late payment 12% per annum in the amount of AED 920.89.

9. This led the Claimant to file a Small Claim against the Defendant for the payment of the Service Charge, as well as the DIFC Courts Fee in the amount of AED 2,382.

The Defence

10. The Defendant filed the Acknowledgment of Service dated 23 November 2017 indicating his intention to defend the whole claim. In his argument at the hearing the Defendant contends that the amount submitted for the service charge are exaggerated and the quality of service does not meet the amount paid. He also added that Claimant did not submit an audit statement of account by a certified accounting office to prove that the expenses have been spent for the maintenance of the building in the previous years. The Defendant did not submit any evidence or documentation in support of his defence.

Hearing

11. In the hearing the Defendant reiterated his arguments, he contends that the numbers provided by the Defendant are not reliable and should come from an auditing company rather than from the Claimant itself.

12. The Claimant replied to those allegations by explaining the procedures the company uses to produce the numbers, as required by the adopted Strata Management System (SMS). The Claimant submitted a copy of the “Strata Management Statement for Hayley LLC” in support of its arguments. This document details that a meeting of the Building Committee may constitute a General Meeting of the Building Body Corporate. At this meeting, Ordinary Resolutions may be issued and then must be approved by each Component Committee. Such Ordinary Resolutions, to include the Annual Budget of the Building Body Corporate, will be sent to all unit owners along with the minutes of the General meeting of the Building Body Corporate.

13. The Claimant pointed out, as indicated on page 5 of the SMS:

“Owners within each Component will pay Service Charges to the Component Body Corporate in relation to Component Common Property and related goods and services. Owners will also benefit from the Principal Common Property and related services and facilities. The Building Body Corporate will charge Building Service Charges to each Component Body Corporate who will pass these costs on to Owners in the form of Component Service Charges.”

14. The Claimant highlighted that the calculations for the service charges had already been submitted to the Defendant during the Consultation phase of the SCT case and even prior to that were sent to the Defendant along with the relevant invoices. The Claimant has also relied on Schedule C of the SMS Document, which states that:

“Component Bodies Corporate and Owners must promptly pay Service Charges and the relevant Committee pursuant to the Strata Title Law has the power to enforce By-laws, or to enforce payment of Service Charges or any other sums properly payable by Component Bodies Corporate or Owners, through the use of the By-laws Compliance Notice procedure and other dispute resolution mechanisms set down in the Strata Title Law.”

Discussion

15. The question put before the Court is, are the amounts invoiced by the Claimant bound legally to be paid by the Defendant or not.

16. Based on the arguments put forward at the Hearing, and based on consideration of the DIFC Strata Law and the SMS Document applicable in this dispute, I am satisfied that the Claimant has proven its position.

17. The Haley LLC Committee of Management at the Annual General Assembly “AGA” prepares the Service Charge Budget with the Body Corporate Manager for each year. This budget includes anticipated expenditures and is shared with the DIFC Registrar at the AGA, and then adopted by simple majority through a resolution with the approval of the DIFC Registrar of Real Property. Such approval would not be granted had the process not been conducted as per the requirements of the DIFC Strata Title Law.

18. The service charge budget of AED 24.64 per sq. ft. for the Defendant’s Property for the financial year 01/06/2015 to 31/05/2016 was approved by the Haley and adopted at the AGA meeting. The Minutes of the meeting have been signed by the Haley LLC Members and have been approved by the DIFC Registrar of Real Property. As such, the service charge calculations go through a lengthy and transparent process to become certified and then these calculations are circulated to all owners.

19. As to the Defendant’s obligation to pay the service charge, as mentioned above, Schedule C of the SMS Document requires that:

“Component Bodies Corporate and Owners must promptly pay Service Charges and the relevant Committee pursuant to the Strata Title Law has the power to enforce By-laws, or to enforce payment of Service Charges or any other sums properly payable by Component Bodies Corporate or Owners, through the use of the By-laws Compliance Notice procedure and other dispute resolution mechanisms set down in the Strata Title Law.”

20. Therefore, it is clear that the Defendant, as an owner in the building, is required to pay the service charges relevant to his Property. The Defendant has not submitted any evidence to suggest or support his allegation that the calculations provided by the Claimant are incorrect or exaggerated. While the Defendant has expressed dissatisfaction with how the service charges have previously been spent and how the building has been maintained, he has not brought any counterclaim and such dissatisfaction does not justify failure to pay. The Defendant has not provided any other defence in support of his failure to pay and therefore it is clear that he must pay the service charges.

Conclusion

21. For the above-mentioned reasons, the Defendant is liable to pay the sum of AED 50,030.56 in addition to AED 2,382 as Court fees.

Issued by:

Maha AlMehairi

SCT Judge

Date of issue: 30 January 2017

At: 12pm

 

The post Haley LLC v Hakon [2016] SCT 199 appeared first on DIFC Courts.

CFI 014/2016 (1) Mr Rafed Abdel Mohsen Bader Al Khorafi (2) Mrs Amrah Ali Abdel Latif Al Hamad (3) Mrs Alia Mohammed Sulaiman Al Rifai v (1) Bank Sarasin Alpen (ME) Limited (2) Bank J. Safra Sarasin

$
0
0

Claim No: CFI-014-2016

THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS

IN THE COURT OF FIRST INSTANCE

BETWEEN

(1) MR RAFED ABDEL MOHSEN BADER AL KHORAFI

(2) MRS AMRAH ALI ABDEL LATIF AL HAMAD

(3) MRS ALIA MOHAMMED SULAIMAN AL RIFAI

Claimants

and

(1) BANK SARASIN ALPEN (ME) LIMITED

(2) BANK J. SAFRA SARASIN (FORMERLY BANK SARASIN & CO) 

Defendants


 ORDER OF ASSISTANT REGISTRAR NATASHA BAKIRCI


UPON reading the Claimant’s Application Notice CFI-014-2016/5 dated 29 January 2017 seeking an amendment to the Consent Order for an extension of time to file Particulars of Claim (the “Application”)

AND UPON reading the First Witness Statement of Roger James Bowden dated 29 January 2017 filed in support

IT IS HEREBY ORDERED BY CONSENT

1.The Application is granted.

2. Paragraph 1 of the Court’s Order of 21 November 2016 is varied so as to read:

  “Pursuant to Rule 7.31(2) of the Rules of the DIFC Courts, time for service of the Particulars of Claim on     the Second Defendant shall be extended until 4.30pm. on 9 January 2017”.

3. Costs in the.

 

Issued by:

Natasha Bakirci

Assistant Registrar

Date of issue: 6 February 2017

At: 4pm

The post CFI 014/2016 (1) Mr Rafed Abdel Mohsen Bader Al Khorafi (2) Mrs Amrah Ali Abdel Latif Al Hamad (3) Mrs Alia Mohammed Sulaiman Al Rifai v (1) Bank Sarasin Alpen (ME) Limited (2) Bank J. Safra Sarasin appeared first on DIFC Courts.

CFI 002/2017 KBC Aldini Capital Limited v (1) David Baazov (2) Canaccord Genuity Corp (3) Canaccord Genuity (Dubai) Limited

$
0
0

Claim No: CFI 002-2017

 

THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS

IN THE COURT OF FIRST INSTANCE

BETWEEN

KBC ALDINI CAPITAL LIMITED

Claimant

and

(1) DAVID BAAZOV

(2) CANACCORD GENUITY CORP

(3) CANACCORD GENUITY (DUBAI) LIMITED

Defendants


ORDER OF JUDICIAL OFFICER MAHA AL MEHAIRI


UPON the Request for Default Judgment made by the Claimant on 6 February 2017 (the “Request”) in accordance with Rule 13.4 of the Rules of the DIFC Courts (“RDC”)

IT IS HELD THAT:

The request is prohibited by RDC 13.4 as the Defendants have filed an Acknowledgment of Service on 31 January 2017 and the time to file a defence has not yet expired.

ACCORDINGLY IT IS HEREBY ORDERED THAT:

The Request is denied.

Issued by:

Maha AlMehairi

Judicial Officer

Date of Issue: 12 February 2017

At: 10am

The post CFI 002/2017 KBC Aldini Capital Limited v (1) David Baazov (2) Canaccord Genuity Corp (3) Canaccord Genuity (Dubai) Limited appeared first on DIFC Courts.

CFI 020/2016 Brookfield Multiplex Constructions LLC v (1) DIFC Investments LLC (2) Dubai International Financial Centre Authority

$
0
0

Claim No:  CFI 020/2016

          THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS 

IN THE COURT OF FIRST INSTANCE

BETWEEN

BROOKFIELD MULTIPLEX CONSTRUCTIONS LLC

                                                                                                                                     Claimant

and

(1) DIFC INVESTMENTS LLC

(2) DUBAI INTERNATIONAL FINANCIAL CENTRE AUTHORITY

Defendants


 CONSENT ORDER


UPON reviewing the correspondence from the parties’ legal representatives

AND UPON reviewing the Consent Orders issued on 4 August 2016, 27 November 2016 and 15 January 2017

AND UPON the parties having agreed the terms detailed in this Order

IT IS HEREBY ORDERED BY CONSENT THAT:

1.The terms of the Consent Order issued on 4 August 2016 (the “Previous Consent Order”) remain fully in effect and all further proceedings in this action continue to be stayed upon the terms set out in the Previous Consent Order, including its Schedule, save that the stay expires on 30 March 2017.

2. Save for the Costs Order referred to in the Previous Consent Order, there shall be no order as to costs.

 

Issued by:

Natasha Bakirci

Assistant Registrar

Date of issue: 13 February 2017

At: 12pm

The post CFI 020/2016 Brookfield Multiplex Constructions LLC v (1) DIFC Investments LLC (2) Dubai International Financial Centre Authority appeared first on DIFC Courts.

Haley LLC v Hakon [2016] SCT 199

$
0
0

Claim No: SCT 199/2016

THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS

 

In the name of His Highness Sheikh Mohammad Bin Rashid Al Maktoum, Ruler of Dubai

IN THE SMALL CLAIMS TRIBUNAL OF DIFC COURTS

BEFORE SCT JUDGE MAHA AL MEHAIRI

 

BETWEEN

 

HALEY LLC

 Claimant 

and 

HAKON 

Defendant

 

Hearing:         3 January 2017

Judgment:     30 January 2017


JUDGMENT OF SCT JUDGE MAHA AL MEHAIRI


UPON the Claim Form being filed on 16 November 2016;

AND UPON the Defendant filing an application to contest jurisdiction on 23 November 2016;

AND UPON a Jurisdiction Hearing being held before SCT Judge Mariam Deen on 28 November, with the Claimant in attendance but the Defendant failing to attend despite receiving sufficient notice of the Hearing;

AND UPON an Order being issued by SCT Judge Mariam Deen on 28 November 2016 finding the Small Claims Tribunal of the DIFC Courts to have jurisdiction to hear the dispute;

AND UPON the parties being called on 5 December 2016 for a Consultation and 12 December 2016 for a Second Consultation with SCT Officer Ayesha Bin Kalban, with the Claimant’s representative and the Defendant in attendance;

AND UPON the parties not having reached settlement;

AND UPON a Hearing having been scheduled before SCT Judge Mariam Deen on 21 December 2016, with the Claimant’s representative in attendance and the Defendant participating via telephone;

AND UPON a Second Hearing having been scheduled before SCT Judge Maha Al Mehairi on 3 January 2016, with the Claimant’s representative in attendance and the Defendant attending by phone;

AND UPON reviewing all documents and evidence submitted in the Court file;

IT IS HEREBY ORDERED THAT:

  1. The Defendant shall pay the Claimant the amount AED 50,030.56 being the service charge for the Defendant’s Property.
  2. The Defendant shall reimburse the Claimant for the Court fee in the sum of AED 2,382.

 

Issued by:

Maha AlMehairi

SCT Judge

Date of issue: 30 January 2017

At: 12pm

THE REASONS

Parties

1. Haley (hereafter the “Claimant”) is a legal entity filing a claim against the Defendant regarding the alleged non-payment of service charges.

2. Hakon (hereafter the “Defendant”) is the owner of Unit, DIFC, Dubai, UAE (the “Property”).

Background and the Preceding History

3. On 16 November 2016 the Claimant filed a claim in the DIFC Courts’ Small Claims Tribunal (the “SCT”) seeking payment by the Defendant of service charges and penalties amounting to AED 50,030.58, relating to the Defendant’s ownership of the Property. The Claimant also sought reimbursement of the Court fee.

4. The Defendant responded to the claim on 23 November 2016 by contesting the jurisdiction of the DIFC Courts and the Small Claims Tribunal over the dispute. A Jurisdiction Hearing was held before SCT Judge Mariam Deen on 28 November with the Claimant’s representative’s oral submissions being heard and the Defendant’s written submissions being considered due to his failure to attend despite receiving sufficient notice of the Hearing. SCT Judge Mariam Deen issued an Order on 28 November 2016 finding the Small Claims Tribunal of the DIFC Courts to have jurisdiction to hear the dispute.

5. The parties were called for a Consultation with SCT Officer Ayesha Bin Kalban on 5 December 2016, and a Second Consultation on 12 December 2016, with the Claimant’s representative and the Defendant in attendance, however, a settlement could not be reached.

6. A Hearing was scheduled before SCT Judge Mariam Deen on 21 December 2016, with the Claimant’s representative attending in person and the Defendant attending via telephone, although due to sickness, the Defendant was unable to give significant oral submissions. Both parties were allowed additional time to make further written submissions and a Second Hearing was scheduled before me on 3 January 2016. 

The Claim

7. The Claimant argues that, on 7 October 2013, pursuant to Strata Title Law (DIFC Law No. 5 of 2007), Haley was established to manage the building Haley LLC, DIFC and this entity is therefore responsible for invoicing all unit owners to pay service charges in order to manage the building.

8. The dispute arising between the parties is in regards to the Defendant’s alleged failure to pay the service charge in relation to the residential in DIFC. The Claimant contends that the Defendant, despite a number of follow-ups and letters, has failed to pay the service charges totalling an amount of AED 50,030.56 which comprises as follows: (the “Service Charge”)

(a) Service charges in the amount of AED 49,109.

(b) Penalty for late payment 12% per annum in the amount of AED 920.89.

9. This led the Claimant to file a Small Claim against the Defendant for the payment of the Service Charge, as well as the DIFC Courts Fee in the amount of AED 2,382.

The Defence

10. The Defendant filed the Acknowledgment of Service dated 23 November 2017 indicating his intention to defend the whole claim. In his argument at the hearing the Defendant contends that the amount submitted for the service charge are exaggerated and the quality of service does not meet the amount paid. He also added that Claimant did not submit an audit statement of account by a certified accounting office to prove that the expenses have been spent for the maintenance of the building in the previous years. The Defendant did not submit any evidence or documentation in support of his defence.

Hearing

11. In the hearing the Defendant reiterated his arguments, he contends that the numbers provided by the Defendant are not reliable and should come from an auditing company rather than from the Claimant itself.

12. The Claimant replied to those allegations by explaining the procedures the company uses to produce the numbers, as required by the adopted Strata Management System (SMS). The Claimant submitted a copy of the “Strata Management Statement for Hayley LLC” in support of its arguments. This document details that a meeting of the Building Committee may constitute a General Meeting of the Building Body Corporate. At this meeting, Ordinary Resolutions may be issued and then must be approved by each Component Committee. Such Ordinary Resolutions, to include the Annual Budget of the Building Body Corporate, will be sent to all unit owners along with the minutes of the General meeting of the Building Body Corporate.

13. The Claimant pointed out, as indicated on page 5 of the SMS:

“Owners within each Component will pay Service Charges to the Component Body Corporate in relation to Component Common Property and related goods and services. Owners will also benefit from the Principal Common Property and related services and facilities. The Building Body Corporate will charge Building Service Charges to each Component Body Corporate who will pass these costs on to Owners in the form of Component Service Charges.”

14. The Claimant highlighted that the calculations for the service charges had already been submitted to the Defendant during the Consultation phase of the SCT case and even prior to that were sent to the Defendant along with the relevant invoices. The Claimant has also relied on Schedule C of the SMS Document, which states that:

“Component Bodies Corporate and Owners must promptly pay Service Charges and the relevant Committee pursuant to the Strata Title Law has the power to enforce By-laws, or to enforce payment of Service Charges or any other sums properly payable by Component Bodies Corporate or Owners, through the use of the By-laws Compliance Notice procedure and other dispute resolution mechanisms set down in the Strata Title Law.”

Discussion

15. The question put before the Court is, are the amounts invoiced by the Claimant bound legally to be paid by the Defendant or not.

16. Based on the arguments put forward at the Hearing, and based on consideration of the DIFC Strata Law and the SMS Document applicable in this dispute, I am satisfied that the Claimant has proven its position.

17. The Haley LLC Committee of Management at the Annual General Assembly “AGA” prepares the Service Charge Budget with the Hayley LLC Manager for each year. This budget includes anticipated expenditures and is shared with the DIFC Registrar at the AGA, and then adopted by simple majority through a resolution with the approval of the DIFC Registrar of Real Property. Such approval would not be granted had the process not been conducted as per the requirements of the DIFC Strata Title Law.

18. The service charge budget of AED 24.64 per sq. ft. for the Defendant’s Property for the financial year 01/06/2015 to 31/05/2016 was approved by the Haley LLC and adopted at the AGA meeting. The Minutes of the meeting have been signed by the Haley LLC Members and have been approved by the DIFC Registrar of Real Property. As such, the service charge calculations go through a lengthy and transparent process to become certified and then these calculations are circulated to all owners.

19. As to the Defendant’s obligation to pay the service charge, as mentioned above, Schedule C of the SMS Document requires that:

“Component Hayley LLC and Owners must promptly pay Service Charges and the relevant Committee pursuant to the Strata Title Law has the power to enforce By-laws, or to enforce payment of Service Charges or any other sums properly payable by Component Bodies Corporate or Owners, through the use of the By-laws Compliance Notice procedure and other dispute resolution mechanisms set down in the Strata Title Law.”

20. Therefore, it is clear that the Defendant, as an owner in the building, is required to pay the service charges relevant to his Property. The Defendant has not submitted any evidence to suggest or support his allegation that the calculations provided by the Claimant are incorrect or exaggerated. While the Defendant has expressed dissatisfaction with how the service charges have previously been spent and how the building has been maintained, he has not brought any counterclaim and such dissatisfaction does not justify failure to pay. The Defendant has not provided any other defence in support of his failure to pay and therefore it is clear that he must pay the service charges.

Conclusion

21. For the above-mentioned reasons, the Defendant is liable to pay the sum of AED 50,030.56 in addition to AED 2,382 as Court fees.

 

Issued by:

Maha AlMehairi

SCT Judge

Date of issue: 30 January 2017

At: 12pm

The post Haley LLC v Hakon [2016] SCT 199 appeared first on DIFC Courts.

CFI 002/2016 DAS Real Estate Owned and Represented by Mussabeh Salem Mussabeh Humaid Al Muhairi v National Bank of Abu Dhabi Pjsc

$
0
0

Claim No: CFI-002-2016

THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS

 

IN THE COURT OF FIRST INSTANCE

BEFORE H.E. JUSTICE SHAMLAN AL SAWALEHI

BETWEEN

DAS REAL ESTATE OWNED AND REPRESENTED BY MUSSABEH SALEM MUSSABEH HUMAID AL MUHAIRI

Claimant

and

NATIONAL BANK OF ABU DHABI PJSC

Defendant


DIRECTIONS ORDER


UPON reviewing the Claimant’s Application Notice CFI-002-2016/3 dated 12 December 2016 that certain key liability issues be determined by way of preliminary hearing (the “Claimant’s Application“), such application being consented to by the Defendant.

AND UPON reviewing the Court file and the Rules of the DIFC Courts (“RDC”)

IT IS HEREBY ORDERED THAT:

Claimant’s Application

1. The Claimant’s Application is granted.

2. The Claimant’s Application having been granted, the parties shall proceed to the determination of certain key liability issues at a preliminary hearing on the basis set out below.

Witness Statements

3. Signed statements of witnesses of fact, and hearsay notices where required by RDC 29.2 and 29.103 to 29.105 inclusive shall be filed and served by the parties by 4pm on Thursday 12 January 2017.

4. Any witness statement in reply shall be filed and served by the later of 4pm on Thursday 9 February 2017 or 4 weeks following the exchange of witness statements.

5. Unless otherwise ordered, witness statements shall stand as evidence in chief of the witness at the preliminary hearing.

Hearing Bundles

6. Agreed hearing bundles shall be completed in accordance with Part 35 of the RDC and lodged by no later than 2 weeks before the preliminary hearing and by no later than 4pm on Monday 20 February 2017. [RDC 35.34]

Reading List

7. A single reading list approved by all parties’ legal representatives for the preliminary hearing shall be lodged with the Registry, together with an estimate of time required for the hearing, by no later than two days before the start of the preliminary hearing, and in any event by no later than 4pm on Thursday 2 March 2017.  [RDC 35.51]

Skeleton Arguments, Opening Statements and Chronology

8. Skelton Arguments and Written Opening Statements shall be served on all other parties and lodged with the Court five clear days before the start of the preliminary hearing for the Claimant, and in any event by no later than 2pm on Monday 27 February 2017 and two clear days before the start of the preliminary hearing for the Defendant, and in any event by no later than 2pm on Thursday 2 March 2017. [RDC 35.62].

Trial

9.The preliminary hearing shall commence on Tuesday 7 March 2017 with an estimated duration of 2-3 days.

10. Costs in the case.

11.  Liberty to apply.

 

Issued by:

Natasha Bakirci

Assistant Registrar

Date of issue: 29 January 2017

At: 11am

The post CFI 002/2016 DAS Real Estate Owned and Represented by Mussabeh Salem Mussabeh Humaid Al Muhairi v National Bank of Abu Dhabi Pjsc appeared first on DIFC Courts.

Hamza v Heidi Law Firm [2017] SCT 004

$
0
0

Claim No. SCT 004/2017 

THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS 

In the name of His Highness Sheikh Mohammed Bin Rashid Al Maktoum,

Ruler of Dubai 

IN THE SMALL CLAIMS TRIBUNAL OF DIFC COURTS

BEFORE SCT JUDGE MAHA AL MEHAIRI 

BETWEEN

HAMZA 

 Claimant 

and

HEIDI LAW FIRM 

Defendant

Hearing:                7 February 2017

Judgment:             14 February 2017


JUDGMENT OF SCT JUDGE MAHA AL MEHAIRI


ORDER

UPON hearing the Claimant and a representative of the Defendant at the Hearing on 7 February 2017

AND UPON reading the submissions and evidence filed and recorded on the Court file

IT IS HEREBY ORDERED THAT:

  1. The Claimant’s Claim is dismissed.
  2. No order as to Costs.

 

Issued by:

Maha AlMehairi

SCT Judge

Date of issue: 14 February 2017

At: 10am 

 

THE REASONS

The Parties

1.The Claimant is a lawyer registered in Dubai.

2. The Defendant is Heidi & Company, a law firm registered in the DIFC located in DIFC, Dubai.

 Background and the Preceding History

3. The Claim arises out of an offer of employment (the “Offer”) received by the Claimant from the Defendant. The Claimant applied for a job with the Defendant, the Claimant went through the interview process with the Defendant, and on 7 June 2016 the Claimant provided the Defendant with a list of references for them to contact on his behalf.

4. There was no communication after that from the Defendant indicating whether they wished to hire the Claimant even though the Claimant consistently followed up with the Defendant. As such, the Claimant accepted another offer to work at a law firm and his joining date was to be on 20 July 2016. On his first working day, the Claimant received a phone call from the Defendant with an offer for him to join the Defendant law firm. On 21 July 2016, the Claimant received the Offer letter from the Defendant, resigned from his current job, and accepted the Defendant’s Offer.

5. The Offer was made subject to the Defendant receiving satisfactory references from the Claimant’s former employers. The Offer letter clearly stated “Thank you for your interest in joining Heidi & Company (“Firm”). We are pleased to offer you the following position, subject to reference checks and police clearance certificate, on the terms and conditions below…” As such, it was clear that there remained a condition on the Offer before it would be finalised.

6. On 17 August 2016, the Defendant issued the Claimant’s visa under the company’s sponsorship, and on 18 August 2016 a joining form was sent to the Claimant in order that the Defendant could finalise the Claimant’s joining formalities. The Defendant did not confirm an exact joining date for the Claimant to start working. There was numerous correspondence between the parties in regards to the Claimant’s joining date and the ongoing delay in the process. At no point did the Claimant receive notice or information that indicated that the Defendant was still going through the reference check process. On 1 September 2016, the Claimant emailed the Defendant’s HR representative requesting to be paid his salary as the delay in joining was caused solely by the Defendant.

7. On 5 September 2016, the Defendant’s HR representative sent an email to the Claimant including a letter informing him that the Defendant was withdrawing their Offer. After receipt of this letter, the Claimant met with the Defendant’s HR representative on 7 September 2016 in order to understand the reasons behind the withdrawal of the Offer, however no satisfactory reasons were disclosed to him during that meeting. Further settlement discussions occurred between the parties but no agreement was reached which resulted in the Claimant filing a case at the DIFC Courts’ Small Claims Tribunal (“SCT”).

8. On 8 January 2017, the Claimant filed a Claim in the SCT against the Defendant. In his Claim Form the Claimant sought the following entitlements (the “Entitlements”):

(i) declaratory relief that the termination of employment was unfair or wrongful;

(ii) AED 21,333 as payment of one month salary;

(iii) AED 28,800 being the loss of income;

(iv) any Court imposed damages with respect to the Claimant’s moral and material damages;

(v) any Court imposed interest;

(vi) the penalty under Article 18 of the DIFC Employment Law;

(vii) AED 1,023.49 as Court fees and legal Costs; and

(viii) any further or alternative relief as the Court sees fit.

The total amount of the Claim was AED 52,197.86 (equivalent to USD 14,203.50).

9. The parties attended a Consultation before SCT Officer Mahika Hart on 24 January 2017, but were unable to reach a settlement. Thus, a Hearing was scheduled before me on 7 February 2017. 

Particulars and Defence

10. It is the Claimant’s case that the Offer was a valid and binding employment offer, which he relied upon and the Defendant’s postponement of the starting date amounted to the Defendant breaching that Offer by preventing the Claimant from starting work at the firm. The Claimant also added that having a valid employment visa under the Defendant’s sponsorship, completing the joining form, and having business cards printed indicates that the Defendant had accepted him as an employee of the firm. An employee at the Defendant’s firm also sent a picture of the Claimant’s name on one of the doors inside the Defendant’s offices. As a result, the Claimant had reason to believe that he was accepted as an employee of the Defendant and was only awaiting confirmation of his joining date. He had no reason to know that his Offer remained conditional upon a finalised reference check.

11. In support of the above entitlements, the Claimant makes arguments under DIFC Law No. 4 of 2005, as amended by DIFC Law No. 3 of 2012 (the “DIFC Employment Law”), DIFC Law No. 6 of 2004 (the “DIFC Contract Law”), DIFC Law No. 5 of 2005 (the “DIFC Law of Obligations”) and DIFC Law No. 7 of 2005 (the “DIFC Law of Damages and Remedies”). The Claimant relies on an employment relationship having been created between the parties via the Offer letter and visa process, or, in the alternative, misrepresentation on the part of the Defendant in inducing him to accept the Defendant’s Offer.

12. On 17 January 2017, the Defendant filed their Acknowledgment of Service intending to defend all of the Claim. The Defendant denied that there was a valid and effective employment contract as the Offer was made conditional on the Claimant providing a reference from his previous employers and this condition had not been satisfied. In support of their argument the Defendant submitted the Witness Statement dated 2 February 2017 a previous employer of the Claimant. In the statement, a previous employer of the Claimant stated that the reference that he gave the Defendant about the Claimant was unfavourable. The Defendant submits that the Offer for employment would have become binding only if the condition precedent of a successful reference check had been completed and as it was not, the Claimant’s Offer for employment never became binding. Therefore, the Claimant is not entitled to any rights as an employee of the Defendant company as the Claimant never became an employee.

13. The Defendant also added that alternatively, in the event that there was a valid contract of employment between the parties, the Defendant would have terminated the Claimant for cause, based on the unsatisfactory reference received from a previous employer of the Claimant.

14. At the Hearing, both parties reiterated their arguments. The Claimant argued that he accepted the Defendant’s Offer and under that Offer he is owed the Entitlements requested in his Claim Form. The Defendant argued that the Offer was conditional upon meeting the condition set out therein and the Claimant failed to meet this condition as indicated above.

Findings

15. The DIFC Courts and the Small Claims Tribunal have jurisdiction over this dispute as it concerns an employment claim within the DIFC and the amount in question does not exceed AED 500,000.

16. This dispute is governed by the DIFC Employment Law, which states:

“Application of the Law

(1) The Law applies to an employee of:

(a) an establishment having a place of business within the DIFC; or

(b) an entity that is created by Law No. 9 of 2004, and the employee is based within, or ordinarily works within or from, the DIFC.

(2) The applicable law to a contract of employment of an employee based within, or who ordinarily works within or from the DIFC, shall be this Law.”

17. Therefore, the Claimant has a valid DIFC employment visa and the Defendant is an entity in the DIFC.

18. First, I will address the issue of what obligations are stipulated under the Offer, and then I will address what, if any, Entitlements the Claimant is eligible to receive under the Offer.

19. This Claim hinges upon whether the acceptance of a valid Offer letter results in creating an employer-employee relationship with the required responsibilities that come with that relationship. Therefore, I turn my attention to the terms of the Offer letter provided to the Claimant by the Defendant.

20. The Offer dated 21 July 2016 which was emailed to the Claimant included the following statement:

“Thank you for your interest in joining Heidi  & Company (“Firm”). We are pleased to offer you the following position, subject to reference checks and police clearance certificate, on the terms and conditions below…”

21. I am satisfied that the Claimant did provide the Defendant with references, however one of the Claimant’s references provided an unfavourable report to the Defendant and the Offer was therefore withdrawn.

22. The critical issue in this case is whether the Offer is subject to certain conditions contained therein. The Offer letter represents a conditional contract, considering that there are specific and necessary conditions required before the Claimant can move forward to sign an employment contract. The fact that the Claimant failed to satisfy the conditions would result in the Offer being revoked.

23. While the Claimant contends that the reference check was complete before the Offer was made, there is no evidence of this in the file. While the Claimant was not given indication that the reference check remained ongoing, he was also never given confirmation that it had been completed, contrary to his claims. Therefore, it was unreasonable for the Claimant to rely upon this conditional Offer as if it were a binding contract of employment, considering that the Offer was conditional as per the plain meaning of the text contained therein. The Claimant is a lawyer and reasonably should have sought clarification as to the status of the conditions set out in the Offer letter. As the Claimant failed to meet the conditions set out in the Offer, it follows that there can be no valid and binding contract of employment between the parties and consequently, the Claim must fail.

24. As the parties never entered into an employment relationship, there is no legal basis for the employment Entailments for which the Claimant has claimed as there is no contractually binding employment relationship between the parties. Furthermore, there can be no claim for misrepresentation under the DIFC Law of Obligations or undue influence under Article 11 of the DIFC Employment Law as the Claimant has failed to meet his burden of proof on these claims; I see no evidence of misrepresentation or undue influence and in fact, the conditional nature of the Offer is obvious from the text of the Offer letter itself. Finally, the declarations requested by the Claimant are inappropriate given the circumstances.

25. For the above reasons, the Claimants claims against the Defendant are dismissed in their entirety.

 

Issued by:

Maha Al Mehairi

SCT Judge

Date of Issue: 14 February 2017

At: 10am

The post Hamza v Heidi Law Firm [2017] SCT 004 appeared first on DIFC Courts.


Haya Spa LLC v Harper Real Estate / Hasan Real Estate [2016] SCT 150

$
0
0

Claim No: 150/2016

THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS

 

In the name of His Highness Sheikh Mohammad Bin Rashid Al Maktoum, Ruler of Dubai

 IN THE SMALL CLAIMS TRIBUNAL

BEFORE SCT JUDGE NATASHA BAKIRCI

BETWEEN 

HAYA SPA LLC

Claimant 

and

HARPER REAL ESTATE / HASAN REAL ESTATE 

Defendant

 

Hearing:          15 January 2017

Judgment:       15 February 2017


JUDGMENT OF SCT JUDGE NATASHA BAKIRCI


UPON hearing the Claimant’s Representative and the Defendant’s Representative;

AND UPON reading the submissions and evidence filed and recorded on the Court file

IT IS HEREBY ORDERED THAT:

1.The Defendant shall pay the Claimant AED 194,400 as damages owed due to the Defendant’s negligence.

2. The Claimant’s claims regarding delayed NOCs, extended fit-out and a new clause to the Lease Agreement are dismissed.

3. The previous SCT Judgment of SCT Judge Mark Beer, issued on 3 October 2016, shall become enforceable upon the expiration of 14 days from issuance of this Judgment.

4. The Defendant shall pay to the DIFC Courts AED 9,692.83 as the remainder of the Court Fee. The parties shall otherwise bear their own costs.

 

Issued by:

Natasha Bakirci

SCT Judge

Date of issue: 15 February 2017

At: 3pm

 

THE REASONS

Parties:

1.The Claimant, Haya Spa LLC, is a DIFC registered company that provides beauty and health care services to women and is represented by the Founder and Managing Director (the “Claimant’s Representative”).

2. The Defendants are Harper Real Estate Development (hereafter “Harper”) and Hasan Real Estate (hereafter “Hasan”) (hereafter, together referred to as the “Defendants”). Harper is the Landlord of retail unitRU-4, DIFC (hereafter the “Premises”). Hasan acts as Harper’s property managing agency. The Defendants’ authorised representative acts for both Harper and Hasan via valid power of attorney (the “Defendants’ Representative”).

Background:

3. On 7 December 2014 the Claimant’s Representative expressed an interest via email to the Second Defendant, Hasan, in leasing the Premises, a retail outlet on the Concourse Floor, DIFC, for fit-out as a Nail Bar. The Claimant’s Representative emailed “I would like to express my interest in leasing the retail outlet of 1,365 square feet in DIFC, for my upcoming Haya, Nail Bar concept … we are offering to pay 158 per square feet for that … Can you also please send me the autocad drawing … [sic]” This email followed a visit by the Claimant’s Representative during which she had been shown UnitRU-4.

4. On 8 December 2014, Hasan’s Leasing Officer responded with a proposed revision to the rent payable with 4 cheques per year and offering a 3 month rent-free fit-out period “… however, if at all, if there is any delay from Hasan side to provide any approval or NOCs, or other documentations that delayed the fit out we can try to extend it, which is subject to confirmation.”

5. On 9 December 2014 the Claimant’s Representative wrote to Hasan stating “[I] would like to confirm my acceptable [sic] of your offer, for the details discussed that will include 3 months fit out period, also for the Rent, with a total of 220,000 a year payable in 4 cheques … Could you please email me the autocad drawing…and highlight on it; where the full glass window is? Just to send it across to my interior designer ?, for a Quick view.? … Could you send the detailed offer letter? As well, in order to move forward quickly?, and Will prepare the deposit cheque …”

6. On 10 December 2014 Hasan’s Leasing Officer sent an email attaching “… the AutoCAD drawings as requested. I shall send you the offer letter later today …” The floor plan provided by the Defendant’s employee identified different spaces in the floor plan using an alphanumerical series beginning unit to include two highlighted units labelled as Unit 11 and Unit 14.

7. On 16 December 2014 the Claimant’s Representative emailed Hasan’s Leasing Officer saying “My designer opened the file, but she was lost, about the exact outlet … which one is it?? There was Units 11, Unit 14, but for Unit 14, the size was smaller Than 1,365 square feet which is the size of my outlet [sic]”.

8. On the same day, Hasan’s Leasing Officer, wrote “Go ahead with Unit 11 please … Anyhow, you may disregard Unit 14.”

9. On 8 February 2015, the Claimant and Defendants entered into a lease agreement for the Premises, retail unit RU-4in DIFC (hereafter the “Lease Agreement”). The Lease Agreement included a “fit-out” period of three months, for which the Claimant would not be required to pay rent. The Lease Agreement states in relevant part:

LEASE AGREEMENT

  1. RENT FREE/FIT-OUT PERIOD: The Landlord agrees to grant the Tenant three (3) months’ rent free/fit-out period starting on 23rd February 2015 and ending on 22nd May 2015. The utility consumption charges and all other charges for the rent free/fit-out period shall be borne by the Tenant. The rent free/fit-out period shall end on the above mentioned date regardless if the Tenant was able to finish its fit-out or obtain its commercial license.

TERMS AND CONDITIONS OF THE LEASE

10. The Tenant has thoroughly inspected the Premises, and the Tenant hereby declares and agrees that the Premises is fit for decoration, fit-out, occupation, usage, free from damage and suitable for the purpose intended by the Tenant.

11.The Tenant shall fit-out and decorate the Premises, and shall be responsible for such fit-out and decorating, using fit-out contractors approved by the Landlord and concerned authorities.

12. The Tenant shall submit to the Landlord for his approval a professionally prepared interior fit-out design drawings and detailed internal and external decorations drawings for the Premises, being fully dimensioned showing floor plan layout, types and colour of material used, the intended theme of the Premises, approximate locations of air conditioning diffusers, sprinkler heads and smoke detectors and any other aspects and details deemed necessary by the Landlord (the “Designs”). Should the Landlord grants his approval on the Designs, then the Tenant acknowledges that the said approval shall be without any kind of warranty, responsibility or liability on the Landlord. In any case, the Tenant understands that the Designs must be finally approved by the concerned authorities.

14. The Tenant’s Designs and fit-out contractors, sub-contractors and consultant must be approved by the concerned authorities and the Landlord.

45. The Tenant undertakes to indemnify and keep the Landlord indemnified against all liabilities, claims, demands, actions, costs, maintenance, water flows, damages or loss arising out of any breach by the Tenant of any of the terms of this Lease.

58. This Lease contains the whole agreement between the Parties and supersedes all previous agreements between the parties relating to this transaction.

59. This lease is subject to the laws of the Dubai and U.A.E. All disputes between the Parties shall be submitted to the exclusive jurisdiction of Dubai Courts. (emphasis in the original)”

10. On 8 March 2015, the Claimant’s Representative requested from Hasan’s Leasing Officer via email to obtain two No Objection Certificates (the “NOCs”) which she required before beginning the fit-out process. The Claimant’s Representative requested by email an update on the issuances of the NOCs on 16 March 2015, 17 March 2015 and 25 March 2015.

11. These NOCs were not obtained until 6 April 2015; the Claimant’s Representative wrote via email on 9 April 2015 to Hasan’s Leasing Officer that NOCs were forwarded to the DIFC for approval and that the fit-out would not likely start until the end of the month. The Claimant’s Representative requested an extension of the fit-out period to accommodate the delay, stating that “We are not able to start paying for rent on May 22nd !! If you delayed me for these weeks to get the NOC.”

12. On 12 April 2015, as part of the approval process, an official from DIFC emailed the Claimant’s Representative asking for a “key plan drawing showing the unit location stamped by Body Corporate.” After some correspondence with the building body corporate, (hereafter referred to as “Body Corporate”), the Claimant received this stamped drawing on 16 April 2015 which highlighted the correct unit, Unit 14 or RU-4or . The Claimant presumably forwarded this stamped and highlighted drawing on to DIFC officials in support of the approval process.

13. On 23 August 2015, the Claimant received approval from the DIFC for its 12 August 2015 application for fit-out in the Premises based on “the submitted concept design of unit RU-4but was requested to obtain “building FM, DEWA, Civil Defense and DCCA technical no objections/fit-out permit prior [to] starting fit-out work at site [sic].”

14. On 14 September 2015, the Claimant’s hired design and contracting company, Contracting LLC (hereafter referred to as the “Contractor”), emailed the Claimant’s Representative to inform her that there had been a misunderstanding as to the correct unit on the AutoCAD drawing and therefore the resulting plans were inaccurate and needed to be redone.

15. That same day, the Claimant’s Representative wrote to Hasan’s Leasing Officer as well as others at Hasan, pointing out that Unit 11 as marked on the AutoCAD drawings provided by Hasan’s Leasing Officer was not the same as unit RU-4referenced in the Lease Agreement. The email also highlighted that “Unit 11”  was written on the wall inside the Premises. The Claimant’s Representative states “This is a complete disaster for me as a business, everything has to be done from 0, and all my business plan and investment forecast has been based on the space, that generates the income, now I’ll have to squeeze everything, have less stations and practically no space for my stock room, It is a real disaster, and a big headache and a lot of loss, for me.”

16. By an invoice dated 21 September 2015, the Contractor charged the Claimant a further AED 160,400 for “Delay Charges due to discrepancy in shop unit As-built drawing & Actual shop [sic].”

17. According to the Claimant’s Representative, Haya Spa opened for business in March 2016 but the Claimant has failed to pay any rent to the Defendant since May 2015. As the Claimant had not paid rent for this period and since the cheques given to the Defendants bounced, the Defendants ordered the Claimant to vacate the Premises and pay all outstanding amounts in a claim filed on 16 June 2016 at the DIFC Courts’ Small Claims Tribunal (the “SCT”).

The Previous Claim and Procedural History:

18. On 16 June 2016, Harper (the Claimant in the Previous Claim) lodged a claim with the SCT against the Claimant (the Defendant in the Previous Claim), in which it claimed that in breach of the terms and conditions of the Lease Agreement, the Claimant had failed to fulfil its obligation in refusing to pay any amount towards rent for a period of 12 months (hereafter referred to as the “Previous Claim”).

19. In the Previous Claim, the parties were unable to reach a settlement and the Claimant failed to formally file its counter claims against the Defendant. Thus, the Judgment of SCT Judge Mark Beer, issued on 3 October 2016, found in favour of Harper for the Claimant’s failure to pay rent pursuant to the valid Lease Agreement between the parties (hereafter referred to as the “Previous Judgment”). SCT Judge Mark Beer also ordered that the Claimant vacate the Premises but granted a stay of execution of the Previous Judgment until resolution of this current Claim was reached.

20. During the proceedings in the Previous Claim, the parties did discuss the application of the DIFC Contract Law, DIFC Law No. 6 of 2004 (hereafter the “DIFC Contract Law”), especially the law of mistake (Articles 37 to 45) but as the Claimant did not formally file a counterclaim, the Previous Judgment did not make formal findings on these issues and instead limited the findings to those relevant to the Claimant’s failure to pay rent under the Lease Agreement.

21. Based on the Previous Claim, the Claimant filed a new case to claim for damages incurred as a result of the Defendants’ alleged failures. The Claimant filed this Claim on 19 September 2016, in advance of the Previous Judgment. As the parties could not reach a settlement of this Claim, the case went for a First Hearing before me on 13 November 2016. After the First Hearing, the parties attempted another settlement conference and upon failing to settle the Claim, attended a Second Hearing before me on 15 January 2017. After the Second Hearing, the parties were permitted to make limited additional submissions after which time the case was reserved for judgment.

The Current Claim:

22. The Claimant’s initial Claim alleged that the Defendant had failed in three regards:

(a) Providing the Claimant with incorrect information regarding the AutoCad floor plan, leading to significant delays and losses on the Claimant’s part.

(b) Delay in providing the necessary NOCs for the Claimant to secure approvals on time.

(c) Misrepresenting the actual size of the Premises, which is about 5% smaller than listed in the Title Deed and advertised to the Claimant.

23. The Claimant argued that due to these failures, most significantly the failure of Hasan’s Leasing Officer to correctly identify the Premises on the AutoCad floor plan provided in December 2014, it suffered damages and losses for which it should be reimbursed by the Defendants.

24. As a result of the above-mentioned failures, the Claimant’s initial Claim Form seeks the following remedies:

(a) Reduction of the rental amount of AED 220,000 per year proportionate with the 5% smaller area of the Premises;

(b) Reimbursement of lost income as per sales reports and other losses due to the Defendants’ conduct, totalling AED 385,500 as per an attachment to the Claim Form, to include contractor fees, lost income, staff salaries and legal costs (later adjusted to AED 419,000 in the Claimant’s Supplemental Submission with the addition of licensing fees);

(c) A change to the Lease Agreement such that it will begin in March 2016 rather than May 2015 (amounting to extension of the rent free/fit-out period by 10 months);

(d) Addition of a new clause to the Lease Agreement which provides that if the Defendants seek to terminate the Lease Agreement, 6-months’ notice will be provided along with an AED 800,000 termination payment;

(e) Extension of the Lease Agreement for two additional years above the three years already included; and

(f) Return of previously provided cheques to be replaced with new cheques.

25. The Claimant clarified and amended its claims in a filing of 21 November 2016 (the “Claimant’s Supplemental Submission”). The basic content of the Claimant’s claim remained the same, with the Claimant contending that the Defendant had a “responsibility” to provide the correct information regarding the AutoCad drawing and due to the “negligence and confusions” caused by providing incorrect information, the Claimant suffered extensive losses and is entitled to damages from the Defendants. The Claimant did adjust the claim for the extended fit-out period to 6 months rather than 10. The Claimant also removed the claims for a reduction of rent based on the alleged actual size of the Premises, extension of the Lease Agreement to five years, and return of previously provided cheques.

26. The above-mentioned remedies were originally valued in the Claim Form at USD 110,775 (equivalent to AED 407,098.13) including the DIFC Courts’ Fee. The Claimant seems to have intended to adjust this claim amount up to AED 500,000 but never paid the requisite fee and thus the amount claimed for official purposes remains at AED 407,098.13.

27. The Claimant submitted extensive evidence in support of its claim including email and letter correspondence between the Claimant, Defendants, Contractor, DIFC officials and Body Corporate. The Claimant also submitted an invoice from the Contractor, layout drawings, the Title Deed for the Premises, photographic evidence of signage in the Premises, daily sales reports, and product collection reports. Finally, the Claimant submitted a witness statement signed and affirmed by the Construction Manager at the Contractor company.

The Defence:

28. The Defendants responded to the Claim in submissions of 8 November 2016, 2 January 2017, 10 January 2017 and 22 January 2017. The bulk of the Defendants’ Defence is contained in their 8 November 2016 submission.

29. The Defendants first challenged the jurisdiction of the SCT over the dispute as the Claimant has claimed remedies with a total value of well above AED 500,000 and the Defendants have not agreed in writing to proceed in the SCT for claims above AED 500,000. The Defendants reiterated this argument in their subsequent submissions.

30. The Defendants addressed the Claimant’s contention that the size of the Premises was smaller than advertised and that the rental amount should therefore be adjusted. As the Claimant has subsequently dropped this Claim from the case, I will not address the details of this argument.

31. The Defendants go on to address the Claimant’s contentions regarding the allegedly incorrect drawing or floor plan provided by Hasan’s Leasing Officer to the Claimant in December 2014. The Defendants cite eight arguments in support of their defence against the Claimant’s contentions surrounding the issue of the floor plan:

(a) The Defendants contend that the drawing provided in December 2014 was an accurate reflection of the floor plan of the building and was not inaccurate in any way.

(b) The Defendants point to Clause 45 of the Lease Agreement which allegedly indemnifies the landlord. Furthermore, Clause 10 states that the Claimant inspected and approved the Premises before signing.

(c) The Defendants cite Clause 58 of the Lease Agreement which states that the written agreement reflects the full extent of agreement between the parties. Since the floorplan was provided in December 2014, well before the Lease Agreement was signed, they argue that it has no legal effect.

(d) The Lease Agreement and all official forms identified the Premises as RU-4.

(e) The Defendants point out that the Claimant received a stamped floorplan from the building body corporate, Body Corporate, on 16 April 2015, which was used to obtain DIFC approvals and which identified the correct unit. The Defendants argue that the Claimant should not have begun work before this approval was received and furthermore, the provision of this stamped floorplan should have caused the Claimant to realize its error at this time.

(f) The Defendants contend that as landlord they were not obligated to send the Claimant a floorplan at all.

(g) The Defendants argue that the Claimant failed to comply with Clause 12 of the Lease Agreement requiring landlord approval of any designs before work has begun. Instead, the Defendants contend, the Claimant sought approval from Body Corporate and the DIFC. Approval from these other parties along with the provision of the correct drawing in April 2015 serve to cut the link of causation between the Defendants’ conduct and the Claimant’s losses. The Defendants cite Articles 10(1) and 11 of the DIFC Law No. 5 of 2005 (hereafter the “DIFC Law of Obligations”) and Article 29(1) of the DIFC Law No. 7 of 2005 (hereafter the “DIFC Law of Damages and Remedies”).

(h) Finally, the Defendants argue that the Claimant has not provided proof that she resubmitted or redid any of the approvals or work that are claimed for against the Defendant.

32. The Defendants address the Claimant’s contention that delay in providing the Claimant with NOCs caused additional loss. The Defendants argue that there was no delay and there is no proof of delay provided by the Claimant. Instead, the Defendants provided any NOCs required from them in a timely fashion. Most NOCs were required from other parties such as building management and government authorities. Furthermore, as the Claimant had failed to pay rent at the time, the Defendants were in their right to withhold their own obligations towards the Claimant.

33. The Defendants also provided numerous objections to the Claimant’s measurement of its losses:

(a) The Defendants claim that there is no proof of payment of the additional amounts to the Claimant’s Contractor once the mistake was discovered in September 2015. Furthermore, the Claimant has not submitted proof of the original costs of the project as compared to the cost to re-do the work. The Claimant has also not submitted any proof of its trade license costs.

(b) As to lost income, the Defendants question the legitimacy of the Claimant’s submitted sales reports as they are not legally prepared documents and they do not indicate profits, only income. Furthermore, the report submitted on 7 December 2016 does not match the report submitted on 27 October 2016.

(c) Regarding the claim for lost staff salaries, the Defendants argue that these staff members were hired after the September 2015 discovery of mistake and the Claimant should have refrained from hiring at a time when the business was not imminently ready to open. Furthermore, the Defendants argue that no proof that the amounts claimed were actually paid out as salaries has been submitted by the Claimant.

(d) In response to the Claimant’s request to change the lease date to March 2016 instead of May 2015, creating an additional 10-month rent-free fit-out period, the Defendants object on three points. First, the landlord is not obligated to provide a rent-free fit-out period or to extend such period. Second, the delay was not solely due to the Defendants’ alleged mistake. Finally, including an additional rent-free period represents double recovery when combined with the other remedies the Claimant is seeking. These arguments did not change when the Claimant reduced the claim to an additional 6-month period, rather than 10 months.

(e) As to the Claimant’s request to amend the Lease Agreement to include a favourable termination clause, the Defendants state that there is no legal basis for such remedy.

(f) The Claimant has removed its claim to extend the Lease Agreement to five years rather than three, thus it is not necessary to detail the Defendants’ arguments regarding such remedy.

34. In the Defendants’ submissions of 2 January 2017, 10 January 2017 and 22 January 2017, the Defendants indicate that they have relied on the Claimant’s Supplemental Submission of 21 November 2016 as a final reflection of the Claim and reiterate their own arguments set out in their submission of 8 November 2016.

35. When the Claimant submitted the witness statement of the Contractor, the Defendants objected that such witness statement is not valid and should be under oath. Furthermore, the statement reflects hearsay and reflects the Contractor’s intent to indemnify itself.

36. Throughout the submissions, the Defendants reiterate that none of their submissions should be taken as an admission and that the Defendants deny all claims against them.

The First Hearing:

37. The First Hearing was not a complete Hearing and instead the parties agreed to stay the case pending further settlement discussions between them. Although some mention of settlement was made at the First Hearing, nothing discussed shall serve to prejudice my judgment moving further. Importantly, the substantive settlement discussions between the parties took place outside of the Hearing.

The Second Hearing:

38. At the Second Hearing, the parties summarised their formal legal arguments.

39. The Claimant asserted that it intends to cap its claim at AED 500,000 to keep the case in the Small Claims Tribunal rather than move it to the Court of First Instance. The Claimant’s Representative, an individual small business owner, contended that she would not be able to continue with the claim in the Court of First Instance and therefore has capped her claim accordingly. The Defendant objected, stating that the claim value adds up to more than AED 500,000 and thus the case should be transferred.

40. The Claimant briefly summarised the Claim, highlighting that the drawings provided by the Defendants on 10 December 2014 were the basis for the design work done by the contractors and architects. The Claimant brought Hans and Mr Hagen to reiterate the contents of the Claimant’s witness statement, to the Defendants’ objection. The Claimant’s Representative also highlighted that she is a layperson and submitted that any further evidence required could be requested from her.

41. The Defendants claimed that the initial drawing provided by their agent was not appropriate for the Contractor to base its work upon. Furthermore, the Defendants emphasised the argument that any causation between the Defendants’ agent’s actions and the Claimant’s losses has been broken by the actions of the Contractor, Body Corporate, and government authorities. While the Defendants’ Representative stated that she did not want to say who specifically is responsible for the Claimant’s losses, she reiterated that the Defendants are not the ones responsible.

42. The Defendants also highlighted that the allegedly incorrect drawing was provided before the final agreement was executed and the final agreement always refers to the Premises by the formal name of “RU-4”. Furthermore, the correct drawing was provided by Body Corporate in April 2015, although the Defendants did not address how this argument would be applied to the time between December 2014 and April 2015. The Claimant responded that the drawing provided in April was also incorrect and furthermore that the Claimant had no reason to distrust the drawing provided by the Defendants’ agent.

43. The Defendants also argued that the Claimant failed to comply with some provisions of the Lease Agreement and that those entities that provided approval for the incorrectly formulated designs should be the ones held responsible.

44. Finally, the Defendants reiterated their objections to much of the Claimant’s provided evidence alleging lack of proof and stressed that none of their arguments should be taken as an admission.

45. While the parties did briefly discuss some of their previous settlement discussions, such information shall not serve to prejudice my judgment.

Findings:

46. At the outset, it is important to note that the parties are not evenly matched when it comes to the ability to make and defend against legal claims. The Claimant is a small business owned and operated by a single representative who has expressed her inability to pay for legal counsel in these proceedings and through her conduct has made clear that she is not well-versed in legal disputes. The Defendants are large companies with in-house legal teams, represented throughout the proceedings by an in-house lawyer with significantly more resources and legal knowledge. While this imbalance shall not serve to sway the outcome of the case, it is relevant to the expected sophistication of the parties’ legal arguments especially for a case before the Small Claims Tribunal.

A. Preliminary Issues

1.Jurisdiction of the DIFC Courts and the Small Claims Tribunal

47. First and foremost, the relevant Lease Agreement states at Clause 59 that “This Lease is subject to the laws of the Dubai and UAE. All disputes between the Parties shall be submitted to the exclusive jurisdiction of Dubai Courts [sic].” Without assessment of this specific clause, it is clear that the DIFC Courts have jurisdiction over the underlying dispute in this case as it relates to property within the DIFC and actions occurring within the DIFC. Therefore, it is clear and undisputed that the DIFC Courts have jurisdiction to decide this matter.

48. Use of the Small Claims Tribunal as a forum within the DIFC Courts requires a second level of jurisdiction requirements to be met. Pursuant to Rule 53.2(1) of the Rules of the DIFC Courts (hereafter the “RDC”), the “amount of the claim or the value of the subject matter of the claim” must not “exceed AED 500,000.” The Defendant has voiced an objection that the amount of the claim is, in fact, in excess of AED 500,000 and therefore the case should be transferred to the DIFC Courts Court of First Instance as the appropriate forum to hear the case. In response to this objection, the Claimant has asserted that it intends to cap its claim at AED 500,000 in order to proceed in the Small Claims Tribunal.

49. As the Claimant has indicated its intention to stay in the Small Claims Tribunal and its understanding that this will require it to cap its claim, I see no reason to transfer the case to the Court of First Instance. This is especially so because the Defendants have not included specific reasons why the case must be heard by the Court of First Instance and because the Claimant’s Representative, who is not a lawyer, asserted that she will not be able to pursue the claim further if transferred to the Court of First Instance.

50. Importantly, transfer of the case will involve a delay in resolution of the matter as the case will begin all over again in the Court of First Instance. While it is frequently in the interest of the defendant to delay the proceedings, this is a unique case where the Claimant has incentive to delay as enforcement of the Previous Judgment is stayed until the conclusion of this case. Still, the Claimant is not seeking to transfer the case and is instead seeking the speediest resolution of the claim.

51. Finally, upon consideration of the factors listed in RDC 53.37, I do not find it appropriate to transfer this case to the Court of First Instance, given that the Claimant has exercised its right to cap its claim at AED 500,000 in order to stay within the remit of the Small Claims Tribunal. Furthermore, the Claimant has not paid her court fees for any amounts beyond the AED 407,098.13 originally claimed in the Claim Form, likely due to an oversight, and thus, the amount in question will in fact be capped at AED 407,098.13 as reflected in the Claim Form and as reflected in the submitted Court Fees.

52. Therefore, as the claim value is less than AED 500,000, this claim is properly before the Small Claims Tribunal of the DIFC Courts.

1. Assessment of the evidence submitted in the case

53. It is important to address the Defendants’ many objections to the evidence submitted by the Claimant, namely the income reports generated by a business application used by the Claimant and the witness statement of the Claimant’s Contractor. RDC 53.48 allows a Judge in the Small Claims Tribunal to accept evidence without strict application of the rules of evidence, giving consideration to the fact that parties are often not represented and are seeking to reduce costs.

54. There is nothing to suggest that the evidence provided by the Claimant is false in any manner. While the Defendants point out that the sales report submitted by the Claimant on 27 October 2016 does not match the sales report submitted on 7 December 2016, these seem to be different reports. The report submitted on 7 December 2016 is entitled “Collection Reports” and reflects charges broken down by type (i.e. waxing, threading, hair cut, hair colour, etc). The report submitted on 27 October 2016 is entitled “Daily Reports” and lists the income collected on each day. It is reasonable to assume that these reports may not match completely and I deem the “Daily Reports” to be the more accurate reflection of income accrued by the Claimant company on a monthly basis.

55. The Defendants contend that the business application used by the Claimant to produce these reports is not a legally approved method of generating income reporting and was not produced by a legal audit. As reflected in RDC 53.48, the evidence need not meet strict standards of evidence law considering the Claimant is a layperson and that there is no reason to suspect that these reports are inaccurate or falsified.

56. As for the witness statement, it shall also be accepted, pursuant to RDC 53.48, but with the qualification that the statements of the Claimant’s Contractor shall only be given weight where they are based on the Contractor’s first-hand knowledge and experience, not based on information provided by the Claimant’s Representative to the Contractor. There is also no reason to suspect that this witness statement is inaccurate or falsified as the Contractor, Mr Hans, signed it and also affirmed its truth in person, at the Hearing of 15 January 2016.

2. Assessment of claims included in the case

57. The Claimant’s original Claim Form included the claims listed at Paragraphs 22 – 24 above. In the Claimant’s Supplemental Submission received on 21 November 2016, the Claimant adjusted the claims, as detailed above.

58. The Defendant has indicated that it deems the Claimant’s Supplemental Submission as a final articulation of the Claim. Therefore, this Judgment shall not address the original claims for an adjustment in rent, extension of the Lease Agreement, or return of previous cheques, which were omitted from the Claimant’s Supplemental Submission. Furthermore, this Judgment will address the claim for an extended fit-out period of 6 months, rather than 10 months as originally claimed.

59. Furthermore, there remain within the case, as per the Claimant’s Supplemental Submission, certain claims that are completely without merit or explanation. First, the claim to add a new clause to the Lease Agreement providing for 6-months’ notice on termination of the Lease Agreement and an AED 800,000 termination payment is wholly without legal explanation or merit and must be dismissed.

60. Second, the Claimant’s claim for losses due to the Defendants’ delay in providing the necessary NOCs for the Claimant to secure approvals on time has been without adequate explanation or proof. Instead, upon review of the evidence provided by both parties, it seems that the Defendants did provide the required NOCs within a reasonable time period of the Claimant’s request and any delay on the part of the Defendants in providing the NOCs did not significantly add to the losses claimed by the Claimant. Therefore, any damages claimed in association with the alleged delay in providing NOCs by the Defendants are unfounded and this claim is dismissed.

61. Thus, there remains essentially one main legal issue in the case: are the Defendants legally liable for the Claimant’s losses due to the communication received from the Defendants’ Leasing Officer misidentifying the Premises on the provided AutoCad drawing? If the Defendants are found liable, the issue of appropriate remedy must also be addressed.

3. Issue of vicarious liability and joint and several liability

62. There has been no contention that the actions of Hasan’s Leasing Officer in providing the AutoCad drawing and misidentifying the relevant Premises on the drawing are not the responsibility of the Defendants under the doctrine of vicarious liability, as Hasan’s Leasing Officer is their authorised agent.

63. There has also been no contention that either Defendant is not joint and severally liable if the Claimant’s claim succeeds as the Defendants are the Claimant’s landlord and the landlord’s appointed agent, respectively.

64. Therefore, I will proceed in this Judgment on the basis that both vicarious liability and joint and several liability apply.

B. Negligence pursuant to the DIFC Law of Obligations

65. The Claimant has made its claim under the legal doctrine of negligence pursuant to the DIFC Law of Obligations. Although the Claimant does not specifically cite the DIFC Law of Obligations, this is the legal basis most clearly referenced in the Claimant’s submission and most clearly responded to in the Defendants’ submissions.

66. In the Claimant’s Supplemental Submission, the Claimant argued that the Defendant owed a “responsibility” to provide the correct information regarding the AutoCad drawing and due to the “negligence and confusions” caused by providing incorrect information, the Claimant suffered loss. While not framed with reference to the DIFC Law of Obligations, this claim essentially states that the Defendants owed the Claimant a duty or responsibility, which they negligently failed to honour, resulting in the Claimant’s losses.

67. While the Defendant cites a number of arguments in defence of this claim, their most meritorious argument is their reference to Articles 10(1) and 11 of the DIFC Law of Obligations and Article 29(1) of the DIFC Law of Damages and Remedies, both of which address the element of causation required under the doctrine of negligence. Therefore, it seems that both parties envisioned the claim to fall under the DIFC Law of Obligations to the point that the Defendant responded to such arguments even though the Claimant did not specifically cite to DIFC Law of Obligations in its submissions.

68. Pursuant to the DIFC Law of Obligations, a party may be liable for negligence if the requirements of Chapter 2 of the DIFC Law of Obligations are met. First and foremost, Article 17 outlines the four required elements of a negligence claim:

“CHAPTER 2: NEGLIGENCE

  1. Liability

(1) A defendant is liable in negligence to a claimant if and to the extent:

(a) the defendant owes a duty of care to the claimant;

(b) the defendant breaches his duty of care to the claimant; and

(c) the defendant’s acts or omissions in breach of his duty of care to the claimant cause loss to the claimant.

(2) The defendant’s liability provided in Article 17(1) shall be reduced by the extent to which the claimant’s negligent acts or omissions contributed to his loss.”

69. As Article 17 of the DIFC Law of Obligations clearly outlines the four elements of a negligence claim as duty, breach, causation and damages, I will address each of these elements in turn.

1. Duty

70. As mentioned in Article 17(1)(a), the Defendants may be liable in negligence if the Defendants “owe[] a duty of care” to the Claimant. Article 18 of the DIFC Law of Obligations elaborates on the requirements under the element of duty, stating:

“18. Duty of care

(1) Subject to Articles 18(2) and (3), a defendant owes a duty of care to a claimant where:

(a) it is reasonably foreseeable that the defendant’s acts or omissions could cause loss to the claimant;

(b) the relationship between the defendant and the claimant is sufficiently proximate for a duty of care to exist; and

(c) it is fair, just and reasonable in the circumstances that the defendant should owe the claimant a duty of care.

(2) A defendant who negligently creates a situation endangering life or property owes a duty of care to a claimant who suffers loss as a direct result of attempting rescue, where it is reasonably foreseeable that rescue could be attempted.

(3) A person only owes a duty positively to act where he has assumed responsibility for the claimant, for certain property or for a third party causing loss to the claimant.”

71. Landlords and tenants typically owe a duty of care to each other, as is appropriate given the relationship that these types of parties have. While the relationship between landlords and tenants is usually governed by the relevant lease agreement, this does not preclude a coexisting duty of care between the parties, although the terms of the relevant contract between the parties may serve to adjust that duty.

72. Pursuant to Article 18(1)(a), it is “reasonably foreseeable” that either a landlord or a tenant’s “acts or omissions could cause loss” to the other party. Pursuant to Article 18(1)(b), the relationship between a landlord and tenant is “sufficiently proximate for a duty of care to exist” considering that both parties will owe responsibilities to the other. Finally, pursuant to Article 18(1)(c), it is “fair, just and reasonable in the circumstances” that both parties should owe a duty of care to the other. Articles 18(2) and 18(3) do not appropriately apply in the circumstances of this case.

73. Admittedly, the Claimant and the Defendants did not enter into their agreed Lease Agreement until 8 February 2015, a full two months after the Defendants’ Leasing Officer provided the information upon which this claim is based. However, this fact does not change the Defendants’ duty to the Claimant for two reasons. First, it is uncontroversial to state that a potential landlord owes a duty of reasonable care to a potential tenant, although this duty may be defined differently than that of a landlord to a tenant. Second, by 9 December 2014, the Claimant’s Representative had affirmatively written to Hasan stating “[I] would like to confirm my acceptable [sic] of your offer.” While it was possible at this point that the parties would not end up executing a valid lease agreement, they were already in the position of landlord and tenant as valid offer and acceptance had already occurred, even if it was not yet reflected in a formal lease agreement.

74. Therefore, it is reasonable to find that the Defendants, as the Claimant’s landlord and the landlord’s agent, owed a duty of care to the Claimant under the DIFC Law of Obligations. I have reviewed the Lease Agreement executed between the parties and find nothing relevant therein to adjust the duty of reasonable care owed by the Defendants towards the Claimant.

2. Breach

75. As established above, the Defendants owe a duty of care to the Claimant as the Claimant’s landlord and the landlord’s appointed agent. The next question is whether that duty was breached by the Defendants, which will require an assessment under the following standard of care, pursuant to Article 21 of the DIFC Law of Obligations:

“21. Standard of care

(1) In order to establish a breach of a duty of care a claimant must show that a defendant failed to exercise reasonable care to avoid causing loss to the claimant, having regard to the probability, and the likely seriousness, of the loss.

(2) “Reasonable care” means the care which a person of ordinary care and skill, engaged in the type of activity in which the defendant was engaged, would have exercised.

(3) A professional person exercises reasonable care if he shows the standard of care of an ordinary skilled person exercising and professing to have the special skill in question.

(4) Where there are different views within a profession about what constitutes reasonable care, a professional shows reasonable care when he takes an approach endorsed or followed by a responsible body of professional opinion.”

76. The facts relevant to the assessment of whether the Defendants breached their duty of care are detailed at Paragraphs 5 – 8 above. The reflection of facts detailed above is not seriously in dispute, although the Defendants continually claimed that there was no mistake on their part. Regardless, it is not in dispute that the Premises that the Claimant rented, identified as RU-4 in the Lease Agreement and Title Deed, is the same as Unit 14in the AutoCad drawing provided to the Claimant by the Defendants’ Leasing Officer on 10 December 2014.

77. When the Claimant’s Representative and her Contractors opened the provided AutoCad, they were understandably confused by the reflection of units therein. The Claimant had expressed interest in renting unitRU-4, advertised as 1,365 Square feet (126.85 Square meters), and had visited this unit as well. The Title Deed for this same unit also listed the area as 1,365 Square feet (126.85 Square meters). However, when the Claimant’s Representative opened the AutoCad drawing provided to her, upon her request, by the Defendants’ Leasing Officer, she found two highlighted units. One unit was identified in green and labelled as “Unit 14” and the other was identified in red and labelled as “Unit 11.” Both units have a square footage listed, neither of which matches the Premises as previously advertised to the Claimant’s Representative.

78. Therefore, as was reasonable, the Claimant’s Representative sought clarification from the Defendants’ Leasing Officer on 16 December 2014. The Claimant’s Representative specifically stated that her designer was lost as to the exact unit and she asked “which one is it?? There was Unit 11, Unit 14, but for Unit 14, the size was smaller Than 1,365 square feet which is the size of my outlet.” This statement reflects that she initially believed the correct unit to be the one labelled as Unit 14 but was confused as the listed square footage was smaller than she expected. That same day, the Defendants’ Leasing Officer replied to her stating “Go ahead with Unit 11 please … Anyhow, you may disregard Unit 14.”

79. In relating the above-mentioned facts to Article 21 of the DIFC Law of Obligations, it is necessary to assess whether the Defendants’ Leasing Officer’s incorrect statement identifying the Premises qualifies as a breach of the Defendants’ duty. As required under Article 21(1), the Claimant must establish that the Defendants failed to exercise reasonable care to avoid causing loss to the Claimant, having regard to the probability, and the likely seriousness, of the loss.

80. In this case, the Claimant’s Representative was understandably confused by the AutoCad drawing sent to her by the Defendants’ Leasing Officer. Furthermore, she expressed that her confusion stemmed from the listed square footage of the two highlighted units, neither of which matched the advertised size of the unit she had expressed interest in and visited. The Claimant also asserted that her designer was similarly confused, indicating that she had sent the drawing on to her designer for review. At this time, 16 December 2014, the Claimant had confirmed that she would rent the Premises and had accepted the Defendants offer in writing via email on 9 December 2014.

81. Based on these facts, it was reasonable for the Defendants’ Leasing Officer to expect that correct identification of the Premises on the AutoCad drawing had commercial implications for the Claimant. On 9 December 2014, when accepting the Defendants’ terms for the lease, the Claimant made reference to her interior designer and asked for the AutoCad drawing of the floor plan “in order to move forward quickly.” Furthermore, upon receiving the AutoCad drawing, the Claimant again expressed that her designer had reviewed the drawing and the square footage between her expected unit and the units in the drawing did not match.

82. It was a failure to exercise reasonable care to affirmatively answer the Claimant’s questions without checking on the highlighted discrepancy in listed square footage as the Claimant had given indication that her interior designer would be using this drawing in order to proceed with the fit-out as quickly as possible. The Claimant’s Representative did also state that the designer would use the AutoCad drawing “for a quick view” on 9 December 2016, but her email of 16 December 2016 more clearly indicated her intention to move forward with her plans as quickly as possible.

83. Should the Defendants argue that their Leasing Officer could not have known the “probability, and the likely seriousness, of the loss” caused by identifying the wrong unit, given that the Claimant and Defendants had not yet executed their formal Lease Agreement, they would not succeed. A person of ordinary care and skill, engaged in leasing properties, would have taken due care to ensure that any documentation provided by the Defendants was accurate and correctly labelled or else provided with the correct disclaimer as to the intended use of the information provided. If there was any doubt as to the accuracy of the information, a leasing officer of reasonable care would mention that uncertainty to the client.

84. The Leasing Officer did not provide a disclaimer, apparently did not check the information provided, in spite of the Claimant pointing out the discrepancy in square footage, and furthermore affirmatively stated “Go ahead with Unit 11 please … Anyhow, you may disregard Unit 14.” This statement understandably served to resolve any question that the Claimant had about the correct unit to move forward with as the Claimant reasonably trusted the information provided by the Leasing Officer and reasonably assumed that the Defendants, engaged professionally in owning and leasing properties, would not provide incorrect technical information as to their own properties. Furthermore, although the square footage for Unit 11 also did not match the advertised size of the Premises, Unit 11 was larger and therefore, the Claimant likely had no reason to object.

85. For the above-mentioned reasons, I find that the Defendants’ Leasing Officer’s affirmative statement that the Claimant should refer to Unit 11 rather than the correct unit of Unit 14 was a breach of the Defendants’ duty of care given the circumstances. I find that Article 21(3) and (4) of the DIFC Law of Obligations are not applicable here as there is no “special skill” involved in the particular action under assessment in this case.

3. Causation

86. As established above, the Defendants have breached their duty of care to the Claimant by providing the Claimant with inaccurate information regarding the Premises. The main crux of the Defendants argument is that the link of causation between the Claimant’s damages and the Defendants’ conduct has been severed by multiple events. Thus, I will address whether causation is present in these circumstances before turning to an assessment of the damages claimed.

87. Pursuant to Articles 10 and 11 of the DIFC Law of Obligations, an assessment of liability under negligence must involve a finding that the Defendants’ conduct caused the Claimant’s losses. The relevant provisions state:

“10. Causation

(1) To establish liability under this Law, a claimant must show that, but for the defendant’s conduct, he would not have suffered loss, and that the defendant’s conduct was a substantial cause of his loss.

(2) Once a claimant has shown that the defendant’s conduct caused his loss, within the meaning of this Article, and assuming that all other requirements for the defendant to be liable are made out, the defendant is liable for the claimant’s entire loss, subject to Chapter 1 of Part 3 and the Law on Damages and Remedies.

11. Intervening act

Where the defendant’s conduct caused loss to the claimant within the meaning of Article 10, the defendant is not responsible for loss to the claimant to the extent that a supervening event has the result that the defendant’s conduct is no longer an operative cause of the claimant’s loss.”

88. Therefore, the Defendants’ actions must be the “but-for” cause of the loss and the “substantial” cause of the loss. Furthermore, there must be no “supervening event” such that the Defendants’ conduct “is no longer an operative cause” of the Claimant’s loss. The Defendants argue that approval of the construction plans by Body Corporate and the DIFC along with the fact that Body Corporate provided the Claimant with the correct drawing in April 2015 served to cut the link of causation between the Defendants’ conduct and the Claimant’s losses. Furthermore, the Defendants argue that the Contractor should not have begun work before approvals were received and that the Claimant failed to comply with Clause 12 of the Lease Agreement. I will address each of these arguments in turn.

89. First, there is nothing to indicate that the Claimant should not have started the process of creating a design for the nail salon from the drawing and information provided from the Defendants on 10 December 2014. The Defendants point to no concrete evidence that would indicate that the AutoCad drawing provided by them was inappropriate to base design work on. In fact, it seems quite clear from the correspondence that the Defendants’ Leasing Officer should have known that the expressed purpose of obtaining the AutoCad drawing was to begin design work. Thus there is no reason why the Claimant’s Contractor, who provided both design and construction work, should not have begun the design work based on the provided AutoCad drawing.

90. Second, it is accurate to argue that the Claimant failed to comply fully with Clause 12 of the Lease Agreement, which states in relevant part that:

“12. The Tenant shall submit to the Landlord for his approval a professionally prepared interior fit-out design drawings and detailed internal and external decorations drawings for the Premises, being fully dimensioned showing floor plan layout, types and colour of material used, the intended theme of the Premises, approximate locations of air conditioning diffusers, sprinkler heads and smoke detectors and any other aspects and details deemed necessary by the Landlord (the “Designs”). Should the Landlord grants his approval on the Designs, then the Tenant acknowledges that the said approval shall be without any kind of warranty, responsibility or liability on the Landlord. In any case, the Tenant understands that the Designs must be finally approved by the concerned authorities.”

92.The Claimant has not shown that it submitted the professionally prepared Designs to the Landlord for approval, although the timing requirements of Clause 12 are not immediately self-evident upon reading. The Clause implies that the Designs should be approved by the Landlord, although the approval implies no warranty. Furthermore, the Clause implies that such approval process is independent of the approval by the “concerned authorities” although a reasonable reading implies that the approval by the Landlord would necessarily need to come before approval by the “concerned authorities.”

93. In any event, failure to comply with Clause 12 of the Lease Agreement only provides the potential for a portion of the delay and loss caused by the incorrect information to be avoided. Presumably, even if the Claimant had provided completed Designs to the Defendants for review, this would only happen upon the completion of those Designs, at significant expense to the Claimant. Furthermore, the Defendants knew of the Claimant’s plans to move forward and did not seek to approve the Designs, at least no request is reflected in the evidence. The suggestion that the Landlord would have reviewed the designs and informed the Claimant as to the correct unit is exactly that, a hypothetical, made all the less convincing considering that it is the Defendants who provided the Claimant with the incorrect information that required correction upon review in the first place.

94. More relevant is the fact that Body Corporate , as part of the approval process, provided the Claimant with a different version of a similar AutoCad drawing on 16 April 2015, indicating the correct unit, Unit 14. While the Claimant contended that this drawing was also incorrect, presumably referring to the square footage listed for each unit in the drawing, the version provided by Body Corporate did identify the correct unit. This should have at least provided the Claimant with notice that there had been an error, either by Body Corporate or by the Defendants, in correctly identifying the unit on the AutoCad drawing and should have caused the Claimant to follow up on the source of the error.

95. While it is quite reasonable that the Claimant relied upon the Defendants’ assertion that the correct unit was Unit 11, it was unreasonable for her to either fail to notice or disregard the discrepancy apparent on 16 April 2015 when Body Corporate provided another version of the AutoCad drawing. As the Defendants argue, this action served to server the link of causation between the Claimant’s full losses and the Defendants’ conduct.

96. While the Defendants may be successful on their argument for lack of causation after 16 April 2015, the Defendants’ Representative did not address how this argument would affect the time period from 10 December 2014 to 16 April 2015. I find that during this time, the Defendants’ actions were both the “but-for” and “substantial” cause of the Claimant’s losses as neither the Claimant or her Contractor would have reason to doubt the Defendants’ information and it is reasonable to assume that the Claimant would begin the expensive design process based upon the technical drawing provided by the Defendants.

4. Damages

96. Having established duty, breach and causation above, the final element of the Claimant’s negligence claim is an accurate assessment of damages in accordance with the DIFC Law of Obligations and the DIFC Law of Damages and Remedies. The DIFC Law of Obligations provides in relevant part:

“20. Economic loss

(1) Where a claimant has suffered only pure economic loss as a result of the defendant’s conduct, the defendant only owes a duty of care to the claimant if:

(a) the requirements of Article 17 are met;

(b) the defendant assumes a responsibility to the claimant;

(c) the claimant relies on the defendant; and

(d) it is reasonable for the claimant to rely on the defendant.

(2) For the purposes of this Article 20, where a person makes a statement, he assumes a responsibility to persons to whom the statement is made or becomes available (such persons being “recipients”) if:

(a) he knows or ought to know that the statement will be communicated to the recipient, either specifically or as a member of an ascertainable class and that it is likely to be acted on by the recipient for the purpose for which the statement was made; and

(b) he intends, or the recipient reasonably believes that he intended, for the recipient so to act.”

97. The DIFC Law of Damages and Remedies provides in relevant part:

“PART 3: DAMAGES IN LAW OF OBLIGATIONS

23. Right to damages

The breach of an obligation under the Law of Obligations gives the injured party a right to damages to compensate the injured party for the losses, pecuniary and non pecuniary, sustained as a result of the breach. The right to damages can either be exclusive or in conjunction with other remedies.

24. Full Compensation

The injured party is entitled to full compensation for loss sustained as a result of the breach of the Law of Obligations.

25. Measure of damages

The injured party has a right to damages as measured by that sum of money which would put him in the same position as he would have been in if he had not sustained the wrong for which he is to be compensated, plus, in each case, any other loss caused by the breach of the Law of Obligations.

27. Certainty of loss

(1) Compensation is due only for loss, including future loss, that is established with a reasonable degree of certainty.

(2) Compensation may be due for the loss of an opportunity in proportion to the probability of its occurrence.

(3) Where the amount of damages cannot be established with a sufficient degree of certainty, the assessment is at the discretion of the Court.

28. Forseeability of harm

(1) Subject to Article 28(2), the party which committed the breach of an obligation under the Law of Obligations is liable for loss which is of a kind that a reasonable man could reasonably have foreseen as a consequence of, and at the time of the commission of, the acts or omissions of the party which committed the breach. 7

(2) In relation to that kind of damage, the liability is:

(a) in the case of pecuniary damage, for the damage so far as it could reasonably have been foreseen; and

(b) in the case of physical damage, for the full extent of the damage, whether foreseeable or unforeseeable in its extent.

29. Loss due in part to injured party

(1) Where the loss is due in part to an act or omission of the injured party or to another event as to which that party bears the risk, the amount of damages shall be reduced to the extent that these factors have contributed to the loss, having regard to the conduct of each of the parties.

(2) This Article does not apply to:-

(a) liability for deceit; or

(b) wrongful interference with property.

30. Mitigation of loss

(1) The party which committed the breach of obligation under the Law of Obligations is not liable for loss suffered by the injured party to the extent that the loss could have been reduced by the injured party taking reasonable steps.

(2) The injured party is entitled to recover any expenses reasonably incurred in attempting to reduce the loss.

(3) The injured party may not increase the damages claimed by his own unnecessary act subsequent to the breach of obligation.

31. Prohibition of double recovery

Where a breach of the Law of Obligations gives rise to liability on the part of two or more parties, and the claimant has recovered a sum from a liable party or parties, then, in proceedings brought by the claimant against other liable parties, the Court shall reduce any award to the claimant to such extent as it thinks appropriate to take account of the sum recovered by the claimant without prejudice to the injured party’s rights to recovery based on the other parties joint and several liability, if any.

32. Interest on damages

Unless otherwise agreed, interest on damages for non-performance of obligations accrues as from the time of non-performance.

33. Manner of monetary redress

Damages, including interest thereon, are to be paid in a lump sum.”

98. As found above, the Defendants’ conduct can only be deemed to be the but-for and substantial cause of the Claimant’s losses until 16 April 2015, at which point the Claimant had adequate notice of the error. The remaining challenge is to accurately measure the damages with due regard to DIFC Law.

99. As a preliminary issue, I find that the qualifications of Article 20 of the DIFC Law of Obligations relevant to a pure economic loss have clearly been met in this case. I have already detailed above that the qualifications of Article 17 have been met. Pursuant to Article 20(1)(b) and Article 20(2), the Defendants clearly assumed a responsibility to the Claimant by providing certain information and asserting the accuracy of that information without disclaimer, having reason to know that the Claimant would rely on that information for commercial purposes. The Claimant reasonably relied on the information provided by the Defendants’ Leasing Officer, having informed her that the information was required in order for her interior designer to begin the fit-out process as quickly as possible. Therefore, although the Claimant has suffered a purely economic loss, the Defendants are still liable for their breach of duty pursuant to Article 20.

100. Pursuant to Articles 23 and 24 of the DIFC Law of Damages and Remedies, the Claimant, as the injured party, has a right to full compensation for the loss sustained as a result of the Defendants’ breach of duty in the form of damages. Pursuant to Articles 25 and 27, the damages should be measured as the sum of money which would place the Claimant in the same position had the Defendants not breached their duty of care but such amount must be established with a reasonable degree of certainty. Article 27 allows some room for estimation and assessment by the Court, as indicated in Article 27(2) and (3).

101. Furthermore, damages are limited, pursuant to Article 28, to those reasonably foreseeable as a consequence of the breach. In this case, damages due to delay in opening the Claimant’s business were reasonably foreseeable as a consequence of providing inaccurate information regarding the layout and floorplan of the rented Premises.

102. Damages are further limited, pursuant to Article 29, when the loss is partially due to the injured party or some other event to which the injured party bears the risk. The amount of damages must be reduced to the extent that other factors have contributed to the loss. In this case, given that I have found above that the link of causation was broken on 16 April 2015, the amount of loss must be reduced to the extent that the Claimant’s failure to notice the error on 16 April 2015 contributed to its losses. I find that the Claimant did not otherwise fail to mitigate damages.

103. Therefore, it becomes necessary to accurately measure the damages caused by the Defendants’ conduct. As indicated above, the correct measure of damages would be the sum of money to place the Claimant in the same position had the Defendants not breached their duty of care. As the Claimant should have discovered the error on or around 16 April 2015, I find that the Defendants are responsible for the loss incurred due to a 4-month delay, from early December 2014 to 16 April 2015. Had the Defendant provided the correct information, the Claimant would have essentially had an additional 4-months to achieve her fit-out and approval process and would have likely opened for business about 4 months earlier.

104. Although measurement of this 4-months’ delay worth of damages is not precise, it is reasonably certain enough to qualify under Article 27 and especially Article 27(3). I find that it is reasonable to assess this 4-month delay at a value of the average monthly income received by the Claimant company once open. This income would serve to cover expenses such as rent and licensing fees, expenses that the Claimant still incurred each month although the business was not yet operational. Based on the “Daily Reports” provided by the Claimant, the Claimant made an average of AED 43,600 per month from April 2016 to September 2016. Thus, 4-months’ worth of lost income amounts to AED 174,400 owed by the Defendants to the Claimant as damages.

105. While the Defendants will object to this measure of damages, considering that they objected to the submission of the “Daily Reports” and claimed that the Claimant had not adequately proven her losses, the Daily Reports are admissible as I have found in Paragraphs 54 – 55 above and the Court has discretion to provide for a reasonably certain assessment of damages pursuant to Article 27(3) of the DIFC Law of Damages and Remedies.

106. In addition to the above-mentioned amount, which serves to cover the Claimant’s loss incurred due to opening for business 4 months later than would likely have been possible had the Defendants not breached their duty of care, the Claimant should be reimbursed for the additional design and fit-out charges paid as a result of having to go through the design process twice. These items are reflected in the 21 September 2015 invoice provided by the Claimant’s Contractor.

107. The Defendant will again object, stating that the Claimant has not provided sufficient evidence to prove that it in fact paid this invoice, but the witness statement provided by the Claimant and accepted into evidence states that the delay charges and penalties “had to be paid” by the Claimant and thus I am satisfied with the Claimant’s evidence on this matter.

108. The 21 September 2015 invoice includes the following charges:

1.Re-preparation of Architectural Drawings, Elevation and Detailed drawings

2. Necessary charges for Revision of 3D design based on the changes in drawings

3. Penalty Fees for delay dated from 12th Sept – 7th Oct 2015 + Govt approval time period

4. Necessary charges to allot more labour for additional 3 weeks due to delay

5. Necessary charges for scaffolding rental for additional 3 weeks

6. Resubmission of All drawings and necessary documentation for all related approvals”

109. The charges reflected under numbers 4 and 5 above clearly do not fall within a reasonable assessment of damages as, had the Claimant discovered the error in April 2015, these charges would likely have been avoided. Furthermore, the Claimant does not seem to have submitted the completed Designs for the first approval by the DIFC until 12 August 2015. This indicates that, had the error been discovered in April 2016, the Claimant would not likely have needed to resubmit all drawings and documentation for re-approval and instead would have included them in August 2015. Thus, items 3 and 6 can also be removed from the measure of appropriate damages. This leaves items 1 and 2 for AED 25,000 and AED 15,000 respectively, totalling an additional AED 40,000 of damages.

110. However, it is possible and quite likely that the Contractors were not completely done with their Designs by 16 April 2015 and therefore, had the error been discovered in April 2015, the charges to redo the Designs would likely have been less. Presumably, the Designs were ready in August 2015 as they were submitted to the DIFC for approval. Thus, the Contractor likely worked on the Designs from December 2014 until July 2015, a period of 8 months. Given that delay from December 2014 until mid-April 2015 is the responsibility of the Defendants and delay from mid-April 2015 until July 2015 is the responsibility of the Claimant, I find it reasonable to assess the Defendants’ responsibility for the cost of redoing the Designs as half of the total cost. This amounts to (AED 40,000 / 2 = AED 20,000).

111. Therefore, in total, the Defendants shall pay the Claimant AED 194,400 as damages for their breach of duty.

C. The Defendants’ remaining arguments

112. The Defendants have submitted for consideration a number of additional arguments which I will address in turn.

113. First, the Defendants contend that the drawing provided in December 2014 was an accurate reflection of the floor plan of the building and was not inaccurate in any way. Furthermore, the Defendant argued that the Lease Agreement and all other official documents always identified the Premises as “RU-4”. These arguments are accurate as statements on their own, but it is uncontested that the information provided by the Defendants’ Leasing Officer was not accurate and was the source of the Claimant’s reasonable reliance and subsequent losses.

114. The Defendants also pointed to Clauses 10, 45 and 58 of the Lease Agreement. None of these Clauses provide a defence to the claim at hand. Clause 10 asserts that the Claimant inspected and approved the Premises, but such inspection does not indemnify the Defendants from any liability for losses due to their negligence.

115. Clause 45 does seek to indemnify the Defendants from any claims arising from the Claimant’s breach of any terms of the Lease Agreement. While the Claimant may have been in breach of Clause 12 of the Lease Agreement, as mentioned above, such breach is not the source of the claim at hand. Rather, the damages due from the Defendants have effectively been reduced to account for the Claimant’s alleged breach in this respect.

116. Finally, Clause 58 of the Lease Agreement states that it represents the entire agreement between the parties and supersedes any previous agreements. However, the supply of the AutoCad drawing and inaccurate information from the Defendants’ Leasing Officer was not pursuant to a previous agreement nor does execution of the Lease Agreement serve to nullify the duty of care owed by the Defendants towards the Claimant.

117. The Defendants also claim that they were not obligated in any way to send the Claimant the AutoCad drawing. This argument is completely beside the point considering that the Defendants’ Leasing Officer did provide the drawing and additionally provided inaccurate information about that drawing. The Defendants lack of obligation to provide the same does not excuse them from liability.

118. Finally, the Defendants argue that the Claimant has not provided proof that she resubmitted or redid any of the approvals or work that is claimed for against the Defendants. The Claimant has submitted a witness statement and invoice regarding the Contractor’s charges. As regards the other approvals, the Claimant has not been awarded damages for those amounts and therefore this argument is moot.

119. The Defendants also provided numerous objections to the Claimant’s measurement of its losses. As the Claimant has not been awarded damages with regard to an extension of the fit-out period or lost salaries, I will not address those arguments here. As to the Defendants’ objections that the Claimant has not provided proof of payment of the additional amounts, proof of resubmitted approvals, or proof of the original cost of the work to the Claimant prior to discovery of the error, I find the Claimant’s evidence to be sufficient for the Court to assess the appropriate losses to a reasonable degree of certainty, in compliance with Article 27(3) of the DIFC Law of Damages and Remedies.

D. Costs

120. The Claimant has also made a claim for legal costs, although it has not articulated an exact amount for these legal costs. RDC 53.70 provides when the SCT can order a party to pay costs. This rule states:

“The SCT may not order a party to a small claim to pay a sum to another party in respect of that other party’s costs, fees and expenses, including those relating to an appeal, except:

(1) such part of any Court or Tribunal fees paid by that other party as the SCT may consider appropriate;

(2) such further costs as the SCT may assess by the summary procedure and order to be paid by a party who has behaved unreasonably.”

121. In this case, I find it appropriate to grant the Claimant half of its Court fee in the amount of AED 9,692.83 as the Claimant has been successful on part of the Claim but has claimed an amount far in excess of the amount awarded. The Claimant has already paid half of the Court fee into the DIFC Courts and therefore, the Defendant shall be required to pay the other half of the fee directly to the DIFC Courts.

122. As for any further costs, the Claimant may argue that the Defendant has behaved unreasonably. However, I do not find the Defendant’s conduct during these proceedings to have met the high threshold of unreasonable behaviour under RDC 53.70(2).

Conclusion:

123. The Defendant shall pay the Claimant AED 194,400 as damages owed due to the Defendant’s negligence.

124. The Claimant’s claims regarding delayed NOCs, extended fit-out and a new clause to the Lease Agreement are dismissed.

125. The previous SCT Judgment of SCT Judge Mark Beer, issued on 3 October 2016, shall become enforceable upon the expiration of 14 days from issuance of this Judgment.

126. The Defendant shall pay to the DIFC Courts AED 9,692.83 as the remainder of the Court Fee. The parties shall otherwise bear their own costs.

Issued by:

Natasha Bakirci

SCT Judge

Date of issue: 15 February 2017

At: 4 pm

 

The post Haya Spa LLC v Harper Real Estate / Hasan Real Estate [2016] SCT 150 appeared first on DIFC Courts.

CFI 026/2016 Dolcezza LLC v Not Applicable

$
0
0

Claim No: CFI 026/2016

THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS

IN THE COURT OF FIRST INSTANCE

IN THE MATTER OF DOLCEZZA LLC

AND IN THE MATTER OF THE DIFC INSOLVENCY LAW NO. 3 OF 2009


ORDER OF H.E. JUSTICE SHAMLAN AL SAWALEHI


UPON reading the Winding-up Petition dated 26 December 2016 (the “Petition”) and the supporting documents filed by DOLCEZZA LLC (the “Petitioner”) pursuant to Part 54 of the Rules of the DIFC Courts (“RDC”), Article 50 of the DIFC Insolvency Law No.3 of 2009, Regulation 8.7.2 of the DIFC Insolvency Regulations

IT IS HEREBY ORDERED THAT:

1.Mr Shahab Haider of Sajjad Haider Chartered Accountants LLP is hereby appointed as Provisional Liquidator of DOLCEZZA LLC, registered in the DIFC under Registration Number 1403, and Commercial License Number CL1403, and with its Registered Offices at Unit DFR P423, Damac Park Towers, Tower 1, Dubai International Financial Centre, Dubai, 2219, United Arab Emirates.

2. The Provisional Liquidator has all the powers as set out in Schedule 3 of the DIFC Insolvency Law No. 3 of 2009.

3. The hearing date for the Petition for winding up is fixed for Tuesday, 7 March 2017, seven days prior to which the advertisement pursuant to RDC 54.62 would be published in accordance with the Practice Direction (PD 3/2011) by no later than Sunday, 26 February 2017.

4. Pursuant to RDC103, which sets out the requirement for the advertisement for appointment, the advertisement shall specifically state that any person intending to appear at the hearing shall give to the Petitioner and the Provisional Liquidator, notice of his intention, specifying whether or not he intends to support or oppose the Petition, and whether or not he objects to the appointment of the Mr Shahab Haider as the Provisional Liquidator, by no later than Monday, 6 March 2017, and if no such notice is provided, then he shall not be able to appear at the hearing of the Petition without further order of the Court.

5. If no notice of objection has been received by Monday, 6 March 2017, a winding up order shall take effect on Tuesday, 7 March 2017 without the need for attendance at a hearing and Mr Shahab Haider of Sajjad Haider Chartered Accountants LLP shall be appointed as Liquidator with immediate effect from the Return Date.

6. The Provisional Liquidator shall be at liberty to apply for such further or other directions as they may deem necessary.

7. The costs of the aforementioned advertisement shall be paid by the Petitioner.

8. Costs of this application shall be dealt with in the liquidation.

Issued by:

Natasha Bakirci

Assistant Registrar

Date of issue: 19 February 2017

At: 3pm

The post CFI 026/2016 Dolcezza LLC v Not Applicable appeared first on DIFC Courts.

CFI 014/2015 Orient Insurance Pjsc v (1) ABN Amro Bank N.V. (2) Bank of Baroda (3) CITI Bank N.A. (4) Credit Suisse AG (5) Emirates NBD Bank Pjsc (6) Mashreq Bank Pjsc (7) Noor Islamic Bank Pjsc (8) Glints Global General Trading llc

$
0
0

Claim No: CFI-014-2015

IN THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS

IN THE COURT OF FIRST INSTANCE

 

ORIENT INSURANCE PJSC

Claimant

and

(1) ABN AMRO BANK N.V.

(2) BANK OF BARODA

(3) CITI BANK N.A.

(4) CREDIT SUISSE AG

(5) EMIRATES NBD BANK PJSC

(6) MASHREQ BANK PJSC

(7) NOOR ISLAMIC BANK PJSC

(8) GLINTS GLOBAL GENERAL TRADING LLC

Defendants


CONSENT ORDER


UPON the Claimant and the Fourth Defendant having fully and finally settled the claim by the Claimant against the Fourth Defendant in Case Number CFI-014-2015 and in the International Chamber of Commerce (“ICC”) arbitration proceedings registered under ICC reference 21435/ZF

IT IS HEREBY ORDERED THAT:

  1. The Consent Order between the Claimant and the Fourth Defendant dated 27 January 2016 be set aside;
  2. That the Case be discontinued pursuant to the Notice of Discontinuance filed by the Claimant on the date of this Consent Order.
  3. There be no order as to costs.

 

Issued by:

Natasha Bakirci

Assistant Registrar

Date of issue 19 February 2017

At: 4pm

The post CFI 014/2015 Orient Insurance Pjsc v (1) ABN Amro Bank N.V. (2) Bank of Baroda (3) CITI Bank N.A. (4) Credit Suisse AG (5) Emirates NBD Bank Pjsc (6) Mashreq Bank Pjsc (7) Noor Islamic Bank Pjsc (8) Glints Global General Trading llc appeared first on DIFC Courts.

DIFC Courts advance with landmark publication of Middle East’s first common law Commentaries

$
0
0

• Authoritative analysis and guidance for legal sector a regional first for common law system

• Fixes reference point for long-term development of commercial law in line with leading global common law courts

Dubai, United Arab Emirates; February 16, 2017: The Dispute Resolution Authority Academy of Law today publishes the first-ever analysis in the Middle East of English language common law created by the DIFC Courts. Designed to guide the legal sector on the rapidly-emerging legal principles and practices set by DIFC Courts since 2008, “Commentaries on the DIFC Laws” represent an important milestone in the development of the region’s leading commercial court.

The Commentaries cements the DIFC Courts’ status as the most mature common law court in the Middle East. Their publication sets the groundwork for further evolution in commercial law, fixing a reference point for long-term development along the lines set by the world’s premier league of commercial courts, such as England & Wales.

DIFC Courts Chief Justice Michael Hwang said: “The publication of this first volume of Commentaries is a mark of the growing maturity of our courts and aligns us with the world’s most established common law jurisdictions. As DIFC common law jurisprudence literally emerges with every new judgment, the need for thoughtful legal analysis becomes imperative for judges, lawyers, and academicians who seek research materials and guidance. This is the key role these commentaries were intended to fulfill, while this body of legal analysis may also provoke new ideas that in turn promote the ongoing development of regional commercial laws and business practices.”

International law firms Jones Day, Clyde & Co, Clifford Chance, Stephenson Harwood, and the late barrister Mr. Stephen Field, wrote commentaries on the most widely used statutes: DIFC Companies Law (Jones Day), DIFC Arbitration Law (Clyde & Co), DIFC Law of Damages and Remedies (Clyde & Co), DIFC Law of Obligations (Clifford Chance), DIFC Employment Law (Stephenson Harwood), DIFC Courts Law (Stephen Field).

David Gallo, Director of the Academy of Law, said: “Publishing these Commentaries was only possible thanks to the hard work and academic contributions of a team of authors from some of the major Dubai-based law firms, and we extend our sincere thanks to all those involved. We would like to pay a special tribute to the late Stephen Field who contributed to the commentaries in an individual capacity and who sadly passed away last year. This first volume of commentaries is dedicated to Stephen’s memory.”

The Academy of Law will commission commentaries on remaining areas of DIFC Laws, and keep the existing commentaries refreshed as the knowledge and application of the laws develop alongside business and technological change.

The post DIFC Courts advance with landmark publication of Middle East’s first common law Commentaries appeared first on DIFC Courts.

CFI 013/2016 Oger Dubai LLC v Daman Real Estate Capital Partners Limited

$
0
0

Claim No:  CFI 013/2016

          THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS

 

IN THE COURT OF FIRST INSTANCE

BEFORE JUSTICE SIR RICHARD FIELD

BETWEEN

OGER DUBAI LLC

                                                                                                                                     Claimant

and

DAMAN REAL ESTATE CAPITAL PARTNERS LIMITED 

Defendant


ORDER OF JUSTICE SIR RICHARD FIELD


UPON considering the correspondence of the parties addressed to the Court contained in letters sent on behalf of the Defendant dated 16 January 2017, 26 January 2017 and 15 February 2017 and letters sent on behalf of the Claimant dated 19 January 2017 and 7 February 2017

AND UPON considering the decision in this matter of the Tribunal appointed under Decree 19 of 2016

AND UPON considering the Court File, including in particular the Administrative Ruling issued by the Chief Justice by letter dated 30 January 2017 (“the Administrative Ruling”) stating that any further proceedings in this matter in the DIFC Courts are put on hold until further notice from the DIFC Court

IT IS HEREBY ORDERED THAT the position remains as stated in the Administrative Ruling which continues to apply.

 

Issued by:

Natasha Bakirci

Assistant Registrar

Date: 19 February 2017

At: 10am

The post CFI 013/2016 Oger Dubai LLC v Daman Real Estate Capital Partners Limited appeared first on DIFC Courts.

CFI 010/2017 ABN Amro Bank N.V. v N/A

$
0
0

Claim No. CFI 010/2017

THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS 

IN THE COURT OF FIRST INSTANCE

IN THE MATTER OF ABN AMRO BANK N.V.

AND IN THE MATTER OF THE REGULATORY LAW (DIFC LAW NO. 1 OF 2004)


NOTE OF JUSTICE SIR RICHARD FIELD


UPON reviewing the Claimant’s Claim Form dated 7 February 2017 seeking an order sanctioning the transfer of part of the Claimant’s business

AND UPON reviewing the Claimant’s Application Notice CFI-010-2017/1 dated 7 February 2017 seeking directions for the claim

AND UPON hearing Counsel for the Claimant, a representative of the transferee and a representative of the DFSA on 21 February 2017

AND UPON reviewing the letter sent by Clifford Chance on 23 February 2017 following the abovementioned hearing

IT IS HEREBY NOTED THAT:

1.The Judge has considered the letter sent to the DIFC Courts Registry by Clifford Chance, the solicitors for the Applicant.

2. Paragraph 4 of that letter in its present form is unacceptable to the Court. What would be acceptable is wording along the following lines:

“The arrangements set out above are proposed as a result of the suggestion made by the Judge and this firm is prepared to act as the scheme report provider only on the basis that if the above arrangements are implemented the application will not be refused by the Court by reason of the fact that the Dubai and Singapore offices of Clifford Chance have acted for ABN AMRO on the [Transaction].”

 

Issued by:

Nassir Al Nasser

Judicial Officer

Date of issue: 26 February 2017

At: 4pm

The post CFI 010/2017 ABN Amro Bank N.V. v N/A appeared first on DIFC Courts.

Collaboration is Key to Securing the Future of MENA Arbitration

$
0
0

Excerpts from a speech by Mark Beer, OBE, Chief Executive, Dispute Resolution Authority
“The Future of International Dispute Resolution Centres: The Garfield Principle” at the Kluwer Law: 5th Annual International Arbitration Summit

Choice is a wonderful thing, but it needs to be sustainable. We have 6 court systems in the UAE. In the MENA region there are 49 centres for arbitration, 50 if the Emirates Maritime Arbitration Centre is included. That’s more than we have Central banks. Most if not all are government funded. Many governments are operating budget deficits, and despite the recovery in the price of oil, all are focusing their expenditure. Are they all needed, is that choice significant? Are they offering what people want? Recent DRA Academy of Law’s Study on governing law & jurisdictional choices in cross-border transactions showed that enforceability, fairness and speed were the three primary reasons for choosing a particular dispute resolution centre. Not arbitration vs. litigation, how pretty or imposing their banner was at a conference, or location.

Whilst choice is good, the number of centres in relation to the number of countries covered suggests trouble looms. But the reality for many centres is that they are declining, investment treaty arbitration is declining. The financial services sector, with some exceptions, prefer efficient commercial courts to arbitration. The reality is that whilst arbitration overall is probably increasing, the increase is not universal, as disputes are going to centres that offer enforceability, fairness and speed, irrespective of location.

And if the closure of an arbitration centre in India might be our Bear Stearns moment, how long before we have our regional Lehmans? How long before one of the region’s 49 or 50 arbitration centres is closed?

What can we do about this? In my view, we need to take action, and soon. The answer is collaboration, As the DIFC Courts has become the most connected commercial court in the world, other Dispute Resolution centres must start to connect and collaborate. Homogenise rules, share marketing resources, cluster the offering to present a unified message and enhance the efficiency of the marketing spend. Share facilities. International arbitration can involve people from all around the world. Technology can allow everyone to connect remotely. Work together to enhance interoperability and enforcement, as well as offering training and development. When these best practices are shared, the stronger centres bring up those in need of support. Success then can be shared. The needs are simple: enforceability, fairness and speed.

Full text of the speech available, please email registry@difccourts.ae

To read the DRA Academy of Law’s “Study on governing law & jurisdictional choices in cross-border transaction” in full please go to: http://www.draacademy.ae/blog/study-on-governing-law-jurisdictional-choices-in-cross-border-transactions/

The post Collaboration is Key to Securing the Future of MENA Arbitration appeared first on DIFC Courts.


World Government Summit: Bringing Order to the Fourth Industrial Revolution

$
0
0

A panel discussion at the recent World Government Summit led by HE Justice Shamlan Al Sawalehi of the DIFC Courts looked at possible answers to the question: ‘How can we bring order to the Fourth Industrial Revolution?’ Laws designed to protect society are simply not evolving as fast as technologies during the Fourth Industrial Revolution. Why is that the case and what can be done?

The answer is not as simple as regulation. Chief Judge Loretta A. Preska, United States District Court for the Southern District of New York, is involved in legal battles where the lines are blurred between technology, science, and medical industries in determining who is at fault and who is liable. She states that there needs to be more of an interdisciplinary approach in which lawmakers, doctors and sociologists can all work together for example.

“If you were to teleport a doctor from the year 1850 and teleport him to a hospital now, that doctor would have no clue what to do. He would not understand anything. But if you teleport a lawyer from 1850 into the legal world of now, all he would need to learn is e-mail and then he could just start work. That is a thought experiment, but tells you a little bit about the world in which we live in today”, said Dr. Sam Muller, Founding Director of the Hague Institute for the Internationalisation of Law (HiiL).

Looking to the future, Gillian Hadfield, Professor of Law and Economics at the University of Southern California points out, “Of course we need all kinds of rules. We need to think about new and innovative ways to develop rules. We can come up with rules that governments could pass that would make a difference. I feel very sure that we will need Artificial Intelligence to regulate Artificial Intelligence. It’s going to be too complicated, we need to get the smart people with investment dollars that are inventing our autonomous systems devoted to the problem of inventing the AI regulatory systems that will make sure that we are comfortable enough getting in cars and getting onto the highways and putting our children in them. There is no such thing as human society without lots of rules.”

The post World Government Summit: Bringing Order to the Fourth Industrial Revolution appeared first on DIFC Courts.

Practice Direction No. 1 of 2017 – Indemnity Costs for Failed Challenges to Arbitral Awards in the DIFC Courts

$
0
0

IN THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS

PRACTICE DIRECTION NO. 1 OF 2017

Indemnity Costs for Failed Challenges to Arbitral Awards in the DIFC Courts

Citation

This Practice Direction will come into effect on the date of signature. It may be cited as Practice Direction 1 of 2017Indemnity Costs for Failed Challenges to Arbitral Awards in the DIFC Courts – and may be abbreviated to PD 1/2017.

 

  1. Where an application has been lodged with the DIFC Courts pursuant to Part 43 of the Rules of the DIFC Courts (RDC) for ratification of an arbitral award, and the award debtor defends such a request for ratification, the presiding judge reserves the right to take into account the merits of such challenge when deciding whether to require the defendant to an arbitration claim to pay the amount of the award into Court first, as security pursuant to Article 44(2) Arbitration Law (DIFC Law No.1 of 2008).[1]

 

  1. Paragraph 1 above shall apply in the context of all applications for ratification of arbitral awards and is not limited to applications under the New York Convention (see footnote 1 below).

 

  1. When the Court is exercising its discretion as to costs under Part 38 of the RDC, the principle of awarding indemnity costs may also be invoked for other unsuccessful applications to Court relating to arbitration, such as (by way of example only) unsuccessful applications for setting aside of arbitral awards and unmeritorious challenges to remove arbitrators. [2]

 

Dated this 27 day of February 2017

 

 

Michael Hwang

Chief Justice of the DIFC Courts

[1] See Article VI of the New York Convention on the Recognition and Enforcement of Foreign Arbitral Awards (“the New York Convention”), which provides as follows: “If an application for the setting aside or suspension of the award has been made to a competent authority referred to in article V(1)(e), the authority before which the award is sought to be relied upon may, if it considers it proper, adjourn the decision on the enforcement of the award and may also, on the application of the party claiming enforcement of the award, order the other party to give suitable security,” reiterated in Article 44(2) of the DIFC Arbitration Law (DIFC Law No. 1 of 2008).

[2] See by way of example the decision of the Hong Kong Court of First Instance in Peter Cheung & Co v. Perfect Direct Limited & Yu Guolin (HCMP 2493/2012) and New Heaven Investments Limited & Rondo Development Limited v. Yu Guolin (HCA 115/2013), judgment of 25 April 2016, where costs were awarded on the indemnity basis where a party had engaged in “unmeritorious” behaviour in attempting to delay the enforcement of an arbitral award; Exfin Shipping (India) Ltd Mumbai v Tolani Shipping Co Ltd Mumbai, [2006] EWHC (Comm): 17 May 2006, where indemnity costs were awarded by the English Commercial Court following a “wholly unmeritorious” application to set aside an arbitral award; and DigiTelCom Ltd. v. Tele2 Sverige AB (1:12-cv-03082), 16 November 2012, where the District Court for the Southern District of New York imposed costs sanctions on a party for making a “frivolous” application to vacate an arbitral award.

The post Practice Direction No. 1 of 2017 – Indemnity Costs for Failed Challenges to Arbitral Awards in the DIFC Courts appeared first on DIFC Courts.

CFI 008/2015 Bocimar International N.V. v Emirates Trading Agency llc

$
0
0

Claim No: CFI 008/2015

THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS

 

IN THE COURT OF FIRST INSTANCE

BETWEEN 

BOCIMAR INTERNATIONAL N.V. 

Claimant

and

EMIRATES TRADING AGENCY LLC

Defendant


  ORDER OF JUDICIAL OFFICER MAHA AL MEHAIRI


UPON reviewing the Defendant’s Application Notice CFI-008-2015/5 and supporting documents dated 11 January 2017 (the “First Application”) seeking permission to stay the case pending the determination of the Joint Judicial Committee (“JJC”) in accordance with Article 5 of Dubai Decree No. 19 of 2016 and the Claimant’s submissions in reply dated 24 January 2017

AND UPON the Defendant’s failure to submit further evidence to support their Application in relation to the JJC case, the details of the case and the Order issued by the JJC to stay all proceedings in DIFC Courts and Dubai Courts

AND UPON reviewing the Defendant’s Application Notice CFI-008-2015/6 and supporting documents dated 31 January 2017 (the “Second Application”) seeking a stay of the proceedings, that the hearing listed for 6 February 2017 be vacated and that various Orders of the Registrar be set aside

AND UPON reviewing the relevant documents on the case file

IT IS HEREBY ORDERED THAT:

1. The First Application and the Second Application be denied.

2. There be no order as to costs.

 

Issued by:

Maha AlMehairi

Judicial Officer

Date of issue: 28 February 2017

At: 3pm

The post CFI 008/2015 Bocimar International N.V. v Emirates Trading Agency llc appeared first on DIFC Courts.

CFI 020/2014 GFH Capital Limited v David Lawrence Haigh

$
0
0

Claim No. CFI 020/2014

CA 002/2016

THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS

 

IN THE COURT OF APPEAL

BETWEEN

GFH CAPITAL LIMITED 

Claimant/Respondent

and

DAVID LAWRENCE HAIGH

Defendant/Appellant


ORDER WITH REASONS OF COURT OF APPEAL


UPON hearing Counsel for the Respondent at a hearing on 18 September 2016 at which the Appellant was not present despite having received notice of such hearing

AND UPON reviewing the following applications made by the Appellant dated 11 September 2016:

(a) Appellant’s application for permission to appeal the directions order of the Chief Justice dated 10 August 2016;

(b) Appellant’s application for permission to appeal the directions order of the Registrar dated 9 September 2016; and

(c) Appellant’s application for various orders of the DIFC Court

AND UPON reviewing the Appellant’s application by way of letter dated 27 November 2016 for a stay in proceedings and for permission to appeal the orders given on 18 September 2016.

AND UPON reviewing the correspondence received on 29 November 2016 from Bryan Cave on behalf of the Respondent

ORDER

IT IS HEREBY ORDERED THAT:

1.The Appellant’s application to appeal against the directions order of the Chief Justice dated 10 August 2016 be struck out.

2. The Appellant’s application to appeal against the directions order of the Registrar dated 9 September 2016 be struck out.

3. The Appellant’s 11 applications by way of letter dated 11 September 2016 be struck out.

4. Costs reserved. Parties to make costs submissions within 14 days of the date of this Order.

 

Issued by:

Natasha Bakirci

Assistant Registrar

Date of Issue: 28 February 2017

At: 4pm

 

 

 

 

REASONS FOR THE ORDER

Brief Background

1.The appeals in this matter arose out of a series of applications made by the Appellant to the DIFC Courts. A brief background is given below to provide context to the matter.

2. The Respondent made a claim over the Appellant’s assets on the basis that the Appellant had allegedly committed fraud by issuing false invoices to third parties, thereby diverting US$ 5 million to his personal bank accounts, in breach of his fiduciary duties to the Respondent.

3. The Appellant was arrested on 18 May 2014 in response to a criminal complaint by the Claimant. He was released from prison on 21 March 2016.

4. The Respondent applied for a freezing order against the Appellant. On 3 June 2014, Deputy Chief Justice Sir John Chadwick granted a freezing order against the Appellant (the “Freezing Order”). The Appellant made various applications to the Court to vary the Freezing Order. In response, Justice Sir David Steel issued three subsequent orders dated 3 May 2015, 14 May 2015 and 28 June 2015.

5. On 14 July 2015, the Appellant made four appeals against the orders of Justice Sir David Steel by way of letter (the “Four Appeals”). Three appeals were made in relation to the amendment of the Freezing Orders so that some of the frozen funds could be released to fund the Appellant’s various court actions and the Appellant could be granted larger sums of maintenance. One appeal was made against Justice Sir David Steel’s refusal to recuse himself from all future proceedings in the matter.

Orders issued in relation to the Appellant’s Four Appeals

6. On 10 August 2016, the Chief Justice issued an order on the Four Appeals made by the Appellant (the “Order of the Chief Justice”). The relevant orders are summarised as follows:

(a) Amount(s) not exceeding AED 130,000 in the aggregate would be released from the Pro Bono Account to a legal representative appointed by the Appellant for the purpose of arguing the Four Appeals before the DIFC Courts. These funds would only be released to the legal representative, not to the Appellant himself, and would only be released after a review of bills rendered by the legal representative.

(b) The Appellant’s appeals for part of the frozen funds to be released to fund the various court actions in which the Appellant was involved (the “Releasing Funds Appeal”) would proceed for hearing on 18 September 2016 (the “Hearing”). The Skeleton Arguments for the Releasing Funds Appeal were to be filed by no later than 2pm on 1 September 2016. Failure to meet the deadline would result in the striking out of the Releasing Funds Appeal. It should be noted that this deadline was extended to 14 September 2016 by emails of the DIFC Courts Registry dated 5 September 2016 and 8 September 2016 respectively.

(c) The Appellant’s appeal for larger sums of maintenance (the “Maintenance Appeal”) and the Appellant’s appeal against Justice Sir David Steel’s refusal to recuse himself from all future proceedings (the “Recusal Appeal”) would be heard on 11 and 12 December 2016. However, skeleton arguments were to be filed by 4pm on 11 November 2016 and any failure to do so would result in the relevant appeal being struck out.

(d) The Claimant’s application for immediate judgment (the “Immediate Judgment Application”) would proceed between 16 and 18 October 2016 in “the absence of any indication to the contrary” by 4pm on 17 August 2016 that Parties would be unavailable on those dates.

7. On 8 September 2016, Registrar Mark Beer issued an order containing directions in relation to the appeal and the immediate judgment application (“Order of the Registrar”). It was ordered that the Appellant’s Releasing Funds Appeal was to be struck out and that the Immediate Judgment Application would proceed between 16 and 18 October 2016.

Applications made by the Appellant prior to the Hearing

8. The Appellant filed three applications on 11 September 2016 (the “Three Applications of 11 September 2016”):

(a) An application to appeal against the directions order of or otherwise reopen the Order of the Chief Justice dated 10 August 2016 (the “Appeal against the Order of the Chief Justice”);

(b) An application to appeal against the directions order of the Registrar dated 9 September 2016 (the “Appeal against the Order of the Registrar”); and

(c) An application for various orders to the DIFC Court (the “Application to the DIFC Court”).

9. The Appellant requested for waiver of fees for the Three Applications of 11 September 2016 or for the Court to consent to the release of fees from his frozen funds.

10. The Appellant sought various orders in its Application to the DIFC Court. A summary of the orders sought are as follows.

(a) A finding that all instructions, pleadings, statements and evidence the Appellant provided to his instructed solicitors and counsel while he was in detention from 18 May 2014 to 24 March 2016 be set aside;

(b) Further or in the alternative, an order staying the Respondent’s claim (the “Claim”) until the United Nations had issued an opinion on “the torture, arbitrary detention, and unfair trial and other serious abuses” of the Appellant’s detention;

(c) Further or in the alternative, an order to adjourn all hearings and the timetable of the Court until one month after he had been released from hospital;

(d) Further or in the alternative, an order striking out or, alternatively, staying the Claim pending the resolution of his civil claim against the Respondent commenced in the Dubai Courts;

(e) Further or in the alternative, an order staying the Claim pending referral to and decision of the judicial tribunal for the DIFC Courts and the Dubai Courts. In the same application, the Appellant also requested for the said referral;

(f) An order releasing funds as reasonably required to enable the Appellant to appoint lawyers and counsel;

(g) An order releasing such frozen funds as may be reasonably necessary to enable the Appellant to obtain local Dubai legal counsel to seek a retrial of case number 2014/19856 based on new evidence which the DIFC Courts had prevented him from filing;

(h) An order releasing funds to enable the Appellant to file a criminal and civil complaint against the Dubai-based party which represented that they would act for the Appellant in defending the Immediate Judgment Application and to which funds of GBP 30,000 were released by the DIFC Court. The Appellant alleged that the Dubai-based party had absconded with the funds;

(i) An order directing the Registrar to respond to the Appellant’s letter of 17 July 2016 and his letters and applications referred to therein;

(j) An order fixing a directions hearing following the alleged “maladministration and bungling” by the Registrar and Ms Lema Hatim of the DIFC Courts; and

(l) An order directing an investigation into Ms Lema Hatim’s handling of the Claim.

11. At the Hearing, Counsel for the Respondent took the Court of Appeal through the Appellant’s Three Applications of 11 September 2016 mentioned in paragraphs 8 and 10 of this Order.

12. The Court of Appeal noted that it would need to hear from the Appellant on his response to the Respondent’s oral submissions. At the Hearing, Chief Justice Michael Hwang stated that the Court would give the Appellant two weeks from the date of receipt of the transcript of the Hearing. The Court would only consider a written submission from the Appellant and there would be no further applications for any reconvening of the Court of Appeal. The response was due on 7 October 2016.

13. On 20 September 2016, the Registrar of the DIFC Courts informed the Appellant of the outcome of the Hearing (the “Registrar’s Letter of 20 September 2016”). The relevant decisions made by the Court of Appeal were as follows.

(a) The Orders of the Court dated 10 August 2016 and 6 September 2016 would stand unamended. The Court noted that there is a typographical error as the Registrar must have intended to refer to the Order of the Registrar dated 8 September 2016.

(b) The Appellant’s Releasing Funds Appeal remained struck out as the Appellant had not fulfilled the condition of filing his skeleton argument by the specified date despite several extensions.

(c) The Claimant’s Application for Immediate Judgment remained fixed for hearing as scheduled on 17 October and 18 October 2016.

(d) The Registrar listed the timelines for the Parties to file their respective witness statements in support of the Immediate Judgment Application.

(e) The Appellant was ordered to file his response to the oral submissions made by the Claimant at the Hearing on 18 September 2016 within two weeks after the transcript and bundle of documents had been delivered to him.

14. In the Registrar’s Letter of 20 September 2016, the Registrar noted that the Court expected service of the transcript and bundle of documents to be effected by 23 September 2016 and the Appellant’s response would be due on 7 October 2016. The Court notes that no response was filed by the Appellant by the due date.

15. By way of letter dated 23 September 2016, the Respondent informed the Court that the transcript and bundle of documents were sent to Keystone Law by courier on 20 September 2016 and received on the same date. The Respondent also informed the Court that a copy of the transcript and bundle of documents was sent to The Bristol Priory, the hospital which the Appellant asserted he was to check into. However, the Respondent was informed by The Bristol Priory that the Appellant was not a patient at that hospital and that there was no patient staying at the Bristol Priory under an assumed name. The Respondents repeated their request for an order that service upon Keystone Law be considered valid service upon the Appellant under rule 9.31 of the Rules of the DIFC Courts (“RDC”).

16. On 6 October 2016, the Court granted the Respondent’s request that service upon Keystone Law be deemed effective service. 

Analysis of the Appellant’s Applications

17. Before the Court elaborates on its analysis, it bears emphasising that the Court is aware that the manner in which the Appellant is presenting his case is unorthodox presumably because the Appellant does not have a lawyer on record representing him in their DIFC proceedings between him and the Respondent. In order to put a speedy end to the Appellant’s applications, the Court is not taking into account any non-compliance of technical requirements relating to forms and payments of fees. Bearing in mind the Overriding Objective under RDC 1.6, it is simply addressing the arguments on its merits.

Applicable law

18. An appellant requires permission to appeal to the Court of Appeal under RDC 44.5.

19. Under RDC 44.89, the appeal Court may:

(1) Strike out the whole or part of an appeal notice;

(2) Set aside permission to appeal in whole or in part;

(3) Impose or vary conditions upon which an appeal may be brought.

20. In accordance with RDC 44.133, the Court of Appeal, on hearing an appeal from a decision of the Court of First Instance, may make the following decisions.

(1) Make or give any order that could have been made or given by the Court of First Instance;

(2) Attach terms or conditions to an order it makes;

(3) Annul or set aside a decision;

(4) Require or prohibit the taking of a specific action or of action of a specified class;

(5) Make a declaration of facts; or

(6) Make any other order that the Court of Appeal considers appropriate or just.

21. As mentioned in paragraph 12 of this Order, the Court ordered the Appellant to file a written response to the oral submissions made by the Claimant at the Hearing by 7 October 2016. However, there was no response from the Appellant by the due date. The Court would therefore have to arrive at its decision without any written response from the Appellant on the Claimant’s oral submissions at the Hearing. In the Appellant’s Appeal against the Order of the Chief Justice, the Appellant submitted that the order was a directions hearing order and that it could not be deemed a judgment of the Court of Appeal. The Appellant argued that the order relating to the Immediate Judgment Application was appealable as it was a matter for the Court of First Instance. He also made an alternative submission that the appeal could be reopened pursuant to rule 44.179 of the RDC, which provides:

“44.179

The Court of Appeal or the Court of First Instance will not reopen a final determination of any appeal unless:

(1) It is necessary to do so in order to avoid real injustice;

(2) The circumstances are exceptional and make it appropriate to reopen the appeal; and

(3) There is no alternative effective remedy.”

22. The Appellant made similar submissions with regard to the reopening of the Appeal against the Order of the Registrar.

Grounds of appeal

23. The grounds of appeal relied on in the Appeal against the Order of the Registrar and the Order of the Chief Justice are similar. It is clear that the Appellant had copied and pasted the grounds of appeal from one application to the other. The grounds of appeal can be briefly summarised as follows.

(a) The Appellant was not served or provided with “the order dated 18 February 2016”. The Appellant was referring to the Registry’s email which granted permission to the Appellant to proceed with the appeals made against the orders issued by Justice Sir David Steel.

(b) The Court scheduled dates when it was impossible for the Appellant to attend court. Accordingly, the Court failed to fully consider the medical evidence that the Appellant was in hospital and was unable to work on his appeals. The Court failed to consider that the Appellant would be unable to travel to Dubai and would be unable to procure a video link to the hospital for the Hearing.

(c) The Court failed to take into account “relevant considerations” by not releasing any of the Appellant’s funds or “sufficient pro bono funds” to enable him to appoint lawyers.

(d) The Court failed to take into account the appeal dated 8 April 2015 which was submitted by Stephenson Harwood and Zafar Ali QC.

(e) The Registrar failed to respond to the Appellant’s repeated requests for copies of all the full appeals, court orders, pleadings and case file.

(f) The Court did not give the Appellant the opportunity to present the medical evidence he submitted.

(g) In relation to the Order of the Chief Justice, the Judge deprived the Appellant of the “standard right of appeal” as the Judge sitting in the appeal court was not entitled to make an order of directions for the lower court, namely, setting the date of the Immediate Judgment Application and directions in relation to it.

(h) The Court erred in procedure, fact and in law in setting a timetable which required the submission of documents and work in the Islamic holiday of EID.

(i) The appeal should be reopened pursuant to RDC 44.179.

24. In all the Appellant’s applications, he emphasised that he was a litigant-in-person and that he did not accept the jurisdiction of the DIFC Court.

25. It is clear that the Appellant had made a myriad of applications to the Court, many of which were convoluted and confusing. For the ease of reference, the Court has categorised the applications into seven main categories.

(a) Applications for permission to appeal against the Order of the Chief Justice and the Order of the Registrar.

(b) Application to reopen the Order of the Chief Justice and the Order of the Registrar pursuant to RDC 44.179.

(c) Application to adjourn all hearings and timetable of the Court until one month after the Appellant has been released from the hospital.

(d) Application for a waiver of fees for the Three Applications of 11 September 2016.

(e) Application to stay or strike out the Claim.

(f) Application to release frozen funds to appoint lawyers and counsel.

(g) Application to investigate into the alleged “maladministration” by the Registrar and Ms Lema Hatim of the DIFC Courts.

26. After reviewing the Appellant’s applications and hearing the oral submissions from the Respondent, the Court dismisses all the Appellant’s applications. The reasons are as follows.

Application for permission to appeal the Order of the Chief Justice and Order of the Registrar

27. The Order of the Chief Justice and the Order of the Registrar were direction orders which focused on the timelines for the Immediate Judgment Application, the Releasing Funds Appeal, the Maintenance Appeal and the Recusal Appeal.

28. These directions were case management decisions. Under RDC 44.30, case management decisions include decisions concerning directions about the timetable of the claim.

29. Under RDC 44.31, where an application is for permission to appeal from a case management decision, the Court dealing with the application may take into account whether (1) the issue is of sufficient significance to justify the costs of an appeal; (2) the procedural consequence of the case management decision; and (3) it would be more convenient to determine the issue at or after trial.

30. As mentioned in the Registrar’s Letter of 20 September 2016, the direction orders of the Chief Justice and the Registrar remain unamended. At the Hearing, the Court rejected the applications, denying the Appellant permission to appeal against the directions orders. The Court now elaborates on its reasons below.

31. The Court takes the view that the Appellant had not demonstrated respect for the RDC and the timelines set by the Chief Justice and the Registrar in the Order of the Chief Justice and the Order of the Registrar.

32. It is clear from the Order of the Chief Justice and the Order of the Registrar that ample time was given to the Appellant to file his skeleton arguments in relation to the Immediate Judgment Application. By the deadline of 1 September 2016, the Appellant still had not filed his skeleton argument. A further extension of the deadline from 1 September 2016 to 7 September 2016 was given, as noted in the Order of the Registrar. The intention was to give the Appellant more time to file his skeleton argument without causing any prejudice to the Respondent. However, no skeleton arguments were filed despite the extension of time.

33. In relation to the Releasing Funds Appeal, the Maintenance Appeal and the Recusal Appeal, the Court has taken into account the Appellant’s circumstances by repeatedly extending the deadline for the Appellant since March 2016. The Court was aware that the Appellant was unrepresented and required some time to obtain legal representation. It therefore gave the Appellant permission to appeal if the Appellant met the condition of filing his skeleton arguments. However, even up to the final deadline of 14 September 2016, the Appellant failed to do so.

34. In this regard, the Court needs to balance the need to give the Appellant a fair opportunity to be heard and the need for the Court to obtain a resolution of the matter within a reasonable time. The consideration of time was important especially because the appeal proceedings have been delayed since the start of 2016 owing to the Appellant’s lack of submissions. 

Legal representation

35. The Court notes that the Appellant was allegedly unable to submit skeleton arguments by the stipulated deadline but was able to write three long applications on 11 September 2016 with more than six pages per application.

36. The Appellant asserted in all his applications that he was a litigant in person. However, it is clear that the Appellant had legal assistance in drafting his letter, in all probability Keystone Law, a law firm which was representing him in judicial review proceedings in England. In Keystone Law’s letter to the DIFC Courts Registry dated 15 August 2016, Keystone Law stated that it was “possible that we shall accept instructions from him to act on his behalf in these appeals.” Keystone Law stated that it was authorised by the Appellant to explain to the Court that he was not in a position to “deal satisfactorily with the various complicated legal and factual issues arising in the DIFC proceedings within the ordered timetable.”

37. While Keystone Law purported to make submissions on behalf of the Appellant, it was careful to say that it was not formally appointed to be the solicitors on record for the Appellant’s DIFC Court proceedings. In Keystone Law’s email to the DIFC Registrar dated 15 September 2016, Keystone Law refused to be the conduit to carry messages back to the Appellant to transmit instructions. Keystone Law informed the DIFC Registrar that the DIFC “should not use us (Keystone Law) as a post box unless and until we are properly instructed.” It is clear that the Appellant was gaming the system as Keystone Law could say anything they liked to the Court without accepting responsibility for being the channel of communication between the Court and the Appellant. In particular, the tactic adopted by Keystone Law gave the Appellant the pretext to deny he had received communications from the Court even though it beggars belief that Keystone Law would not have been furnishing the Appellant with copies of the Courts’ replies to their various letters or at least informing the Appellant of the contents of the Courts’ replies.

38. Despite this ambivalence, it is clear that Keystone Law had the authority to write on the Appellant’s behalf. The Court had also extended further indulgence to the Appellant in considering Keystone Law’s letters notwithstanding their lack of official status as Haigh’s appointed lawyers.

39. It is clear that the Appellant conveniently used Keystone Law to act as his messenger whenever it suited him and to deny receiving information from the Court even if it had been furnished to Keystone Law.

40. Additionally, the Appellant had, in his correspondence with the Court and the Respondent, informed the court that there was no fixed address at which he could accept service of any documents in person or otherwise by electronic means.

41. In his email from dhaighlegal@gmail.com to the DIFC Registrar dated 16 May 2016, the Appellant stated that he was “unable to accept any service to this email or otherwise until I have a fixed abode.”

42. In the Appellant’s email to the Respondent dated 16 May 2016, the Appellant repeated that he had “no fixed abode and therefore no address for service.” He also stated that he would accept service once he had a fixed abode. The Respondent made efforts to verify the authenticity of his gmail account. The Respondent contacted the Appellant’s lawyers, Kaim Todner Solicitors, who represent him in a judicial review arising out of his attempt to prosecute the Respondent’s executives, to confirm the authenticity of the gmail address. However, Kaim Todner Solicitors refused to give any confirmation.

43. On 20 May 2016, the Respondent obtained an email from lawyers who represented Sport Capital Ltd, whose ultimate beneficial owner is the Appellant. The email, sent from an account of david@davidhaigh.co.uk, reflected the Appellant’s consent to a revised consent order. In the Appellant’s letter to the DIFC Courts Registry dated 17 July 2016, the Appellant informed the Court to cease emailing to the address of david@davidhaigh.co.uk as it was “insecure”. He emphasised that any correspondence should be sent to his gmail account of dhaighlegal@gmail.com. Despite his insistence that correspondence should be sent to dhaighlegal@gmail.com, he continued to state in the same letter that he could not accept service by email as he did not have any means to print and did not have ready access to a computer.

44. The Respondent informed the Court that it had attempted to contact the Appellant via the email address dhaighlegal@gmail.com. However, when the Respondent’s lawyers sent emails to that gmail account, they were met with an ”Out of Office” message which stated that “I am undergoing medical treatment as an inpatient and will not be able to deal with your email at present. I will deal with your email upon my return.”

45. Under RDC 9.15, a party must give an address for service within the DIFC or Dubai. A physical address in Dubai or the UAE will not be required if an email address is given. In the present matter, even though the Appellant emailed the Court and the Respondent with various email addresses, he specified that he could not accept service of documents via electronic means.

46. Under RDC 9.19, where no legal representative is acting for the party to be served and the party has not given an address for service, the document must be sent to the individual’s usual or last known residence. Under RDC 9.21, a party or his legal representative who changes his address for service shall give notice in writing as soon as it has taken place to the Court and every other party. According to the Appellant, he has no fixed abode for service of documents. Without any fixed place of residence or any email which could be used for service of documents, it is clear the Appellant wanted to receive correspondence and communicate only when it was convenient for him.

The Appellant’s medical condition

47. The Appellant claimed in the Three Applications of 11 September 2016 that he was on medication which was “such to diminish my [his] mental capacity and ability to work”. The Appellant gave Morphine, Tramadol, Diazapaam, Xanax, Clompazapm Imigran, Escitalopram as some examples of the medication he was taking. He submitted that it was hard for him to stay awake and near impossible to focus or recall events. He stated that he was “comprehensively disabled” until the completion of his treatment, which was estimated to be “late October early November 2016”.

48. The Appellant had previously presented a medical report by Dr Az Hakeem dated 21 June 2016 (the “Medical Report by Dr Hakeem”). In his covering letter, Dr Hakeem noted that the report was based on an initial psychiatric assessment on 21 June 2016. Dr Hakeem confirmed that the Appellant was “too unwell to attend for work and I (Dr Hakeem) envisage will remain too unwell for approximately the next month.” The Medical Report by Dr Hakeem provided a history of the circumstances of the Appellant’s detention in Dubai. Dr Hakeem advised the Appellant “not to have any contact with any of those persons involved in his detention, torture or abuse, or others whom he deems to have had a negative impact upon his mental state, connected to these events.”

49. Additionally, the Appellant was advised to avoid involvement in situations relating to the traumas experienced which including “legal proceedings that are connected to the traumatic events experienced.”

50. According to the Appellant, he was diagnosed with Post Traumatic Stress Disorder (“PTSD”) and Severe Depression. After reviewing the Medical Report of Dr Hakeem, the Court notes that the report was only an initial psychiatric assessment. The diagnosis of PTSD and Severe Depression were the impressions of the initial assessment.

51. The Court notes that the Medical Report by Dr Hakeem did not comment on the mental capacity of the Appellant. It did not state that the Appellant was unable to read or comprehend legal documents, or give instructions to his legal counsel regarding the conduct of this matter. The Appellant was advised not to recount the unpleasant memories and legal proceedings which related to his incarceration in Dubai, rather than the civil proceedings in Court. In fact, the Appellant chose not to follow the medical advice given by the doctor by writing letters to the Court and instructing Keystone Law.

52. In the Appellant’s Application to the DIFC Courts, the Appellant submitted that he had a change in circumstances by presenting a medical report by Dr Ben Laskey dated 12 June 2016 (the “Medical Report by Dr Laskey”). The Appellant explained in his Application to the DIFC Court that he had not submitted the Medical Report by Dr Laskey previously “due to the very personal nature of the report and the previous wholly criminal behaviour of the Claimant and the irresponsible behaviour of this Court, causing me to be beaten and raped in Jail by making public, on its YouTube channel (notwithstanding my solicitor’s application for the hearing to be private) my sexuality.” The Appellant stated that the Medical Report by Dr Laskey “clearly confirmed the diagnosis of Post-Traumatic Stress Disorder” made in the Medical Report by Dr Hakeem and confirmed the “urgency” of the Appellant’s need to get treatment.

53. Dr Laskey stated that his report was based on his meeting with the Appellant for around 60 minutes, on a pro bono basis, on 27 May 2016 for a discussion about his mental health and emotional coping following his release from prison. The Medical Report by Dr Laskey opined that he was suffering from significant emotional distress and symptoms consistent with PTSD. Dr Laskey stated that he believed that the Appellant’s symptoms would “meet the diagnostic threshold for PTSD”. However, he also noted that he had not conducted a formal diagnostic assessment.

54. Taking the medical reports at face value, it is clear that the Appellant was in a position to proceed. The Appellant’s physical presence was not essential. The option of appearance by way of video link was also offered to the Appellant in paragraph 5 of the Order of the Chief Justice. Even if the Appellant was physically disabled to attend the Hearing, arrangements could have been made for him to instruct lawyers to be present on his behalf. If the Appellant’s representatives or lawyers had appeared on his behalf and apologised for his absence, there was no doubt that the Court would have into taken consideration his personal circumstances.

55. Furthermore, if the Appellant’s need for medical treatment was “urgent”, the Appellant would not have waited until 17 September 2016 – three months after the medical reports were written, and just a day before the Hearing – to be admitted into hospital.

56. In the Appellant’s Application against the Order of the Chief Justice and the Application against the Order of the Registrar, the Appellant stated, “at the time of writing this application I am now hours away from inpatient treatment at a psychiatric hospital.” The Applications were dated 11 September 2016. At the Hearing, the Respondent informed the Court that, according to the Appellant’s Twitter feed, he did not check into hospital until 17 September 2016, one day before the Hearing.

57. The Hearing was scheduled almost six months after the Appellant had been released from prison on 24 March 2016. It is clear that the Appellant kept using medical records to delay the proceedings but only chose to admit himself into hospital just before the date of the Hearing. The Appellant had strategically timed his medical appointments and inpatient treatment dates in an effort to delay the proceedings in the DIFC Courts.

58. In addition, the Court notes that the Appellant had enough mental and physical capacity to instruct Keystone Law to write letters, as explained in paragraphs 36 to 39 The Appellant could have instructed these lawyers to argue the Appeals but instead, he chose to instruct them only to write letters.

59. The Appellant abused the system by using Keystone Law both as a sword as well as a shield but refused to allow Keystone Law to perform the full and proper role of a lawyer representing a party, namely, to represent and act for him. In other words, it was simply a one way street and inconsistent with the proper function of a legal representative.

Other grounds of appeal

60. The Appellant contended that the Court failed to take into account the appeal dated 8 April 2015 which was submitted by Stephenson Harwood and Zafar Ali QC (“Appeal dated 8 April 2015”).

61. The Appeal dated 8 April 2015 was filed against the Judgment of Justice Sir David Steel dated 25 March 2015. The Judgment of Justice Sir David Steel dated 25 March 2015 was the result of the Appellant’s application to vary a freezing order issued by Justice Sir David Steel where the Appellant was restrained from disposing of his assets.

62.The Appellant was wrong in contending that the Court failed to take into account the Appeal dated 8 April 2015. The Court clarifies that, while the appeal notice was filed, it was not paid for and never accepted. Accordingly, there was no live appeal before the Court. In addition, shortly after the appeal notice was filed, the Appellant’s former representatives, Stephenson Harwood, refused to act on the basis that they were not paid by the Appellant. In May 2015, Stephenson Harwood came off the record and made no intention to pursue the Appeal dated 8 April 2015. The Appellant made no further attempts to pursue the Appeal dated 8 April 2015.

63. The Appellant also argued that, in relation to the Order of the Chief Justice, the Judge deprived the Appellant of the “standard right of appeal” as the Judge sitting in the appeal court was not entitled to make an order of directions for the lower court, namely, setting the date of the Immediate Judgment Application and directions in relation to it.

64. As a matter of case management, and taking into account the Appellant’s personal circumstances in defending the Immediate Judgment Application, the Court had intentionally scheduled the hearing for the Immediate Judgment Application after the Releasing Funds Appeal so that the Appellant would have the opportunity to present his case. If the Appellant was successful in the Releasing Funds Appeal, he would be able to avail himself of funds to be used in the Immediate Judgment Application. This was a case management decision by the Court, bearing in mind the Overriding Objective under RDC 1.6 to ensure that the case was dealt with expeditiously and fairly.

65. Based on the reasons cited above, the Court concludes that any appeal against the timelines for the Immediate Judgment Application, the Releasing Funds Appeal, the Recusal Appeal and the Maintenance Appeal would be futile as the Appellant had demonstrated that he was clearly attempting to delay the progress of these cases. The Appellant had abused the system by refusing to give a proper address for service and by placing himself outside the realm of contact by the DIFC Courts.

66. The Appellant’s applications are therefore dismissed.

67. Nevertheless, the Appellant may make fresh applications for the release of frozen funds and maintenance if he believes that circumstances have changed to a significant degree to justify a new application for relief. With regard to the Recusal Appeal, it is open to the Appellant to file an extension of time under RDC 44.41, if and when Justice Sir David Steel is assigned to hear any matter involving the Appellant.

68. With regard to the Immediate Judgment Application, the hearing and consequently, the judgment, had been issued on 18 October 2016. Accordingly, the Court cannot relook the timelines given on the Immediate Judgment Application. However, the Court notes that the Appellant had applied for permission to appeal the Judgment of Justice Roger Giles dated 18 October 2016. Any issues regarding the Immediate Judgment Application will be dealt with in the Appellant’s application for permission to appeal.

69. In arriving at these decisions, the Court has taken into account the Overriding Objective under RDC 1.6 in disposing of contentious issues in the most cost and time efficient manner possible while respecting due process. In other words, the Court will not necessarily require each contested issue to be tried and to have related applications heard by separate courts, but will deal with them in a practical manner to reconcile Parties’ need for determination of essential issues with procedural efficiency. 

Application to reopen Order of the Chief Justice and the Order of the Registrar pursuant to RDC 44.179

70. RDC 44.179 provides that the Court of Appeal will not reopen the final determination of an appeal unless (1) it is necessary to do so to avoid real injustice; (2) the circumstances are exceptional and make it appropriate to reopen the appeal; and (3) there is no alternative effective remedy.

71. Justice Roger Giles examined the application of RDC 44.179 in Raul Silva v. United Investment Bank Claim No: CA-004-2014 (“Raul Silva”). This position in Raul Silva was repeated in the Order of Justice Sir David Steel dated 27 April 2015 in (1) Roberto’s Club LLC (2) Emain Kadrie v Paolo Roberto Rella CFI 019/2013.

“5.  RDC.44.179 is modelled on the English CPR 52.17 introduced in 2003 after the decision in Taylor v. Lawrence [2002] EWCA Civ 90; [2003] QB 528 that there was an inherent jurisdiction to reopen an appeal in order to avoid real injustice in exceptional circumstances.  In In re Uddin (A Child) [2005] EWCA Civ 52; [2005] 1 WLR2398 it was said at [18] that it must generally be demonstrated “that the integrity of the earlier litigation process…has been critically undermined” and “the process itself has been corrupted”, and that “it is the corruption of justice that as a matter of policy is most likely to validate an exceptional course; a course which relegates the high importance of finality in litigation to second place”.

6. An appeal is not to be reopened so that a party can relitigate a matter already considered or present the matter more fully or better than it may have been previously presented, even if the application is based on mistakes by the party’s lawyers…The jurisdiction must be exercised with caution, given the importance of the public interest in the finality of litigation. Generally it will not be exercised unless the applicant can show by accident and without fault on his part he has not been heard or his appeal has not been fully considered, although there may be other circumstances in which, for example, misapprehension of the facts or the law has fundamentally afflicted the integrity of the judgment in question.”

72. The Appellant argued that the appeal must be re-opened as there was no hearing allowed for the directions hearing or that there was “no consideration or examination and presentation of the medical evidence”.

73. As mentioned in paragraphs 27 to 34 of this Order, the directions given were case management decisions. To re-open the appeal, the Appellant had to show that the integrity of the earlier litigation process had been undermined. The Appellant was given numerous extensions so that he would have had time to obtain legal representation to meet the deadline to file skeleton arguments.

74. It is clear that there was no real injustice to the Appellant as he is entitled to make fresh applications as stated in paragraph 67 of this Order. The Court does not consider the reopening of directions orders as exceptional circumstances. The Court also disagrees that there was no consideration or examination of the Appellant’s medical evidence and refers to paragraphs 47 to 59 of this Order.

75. Accordingly, the Appellant’s applications to re-open the Order of the Chief Justice and the Order of the Registrar pursuant to RDC 44.179 are dismissed.

Application to adjourn all hearings and timetable of the Court until one month after the Appellant has been released from the hospital

76. The hearing dates and timetable of the Court are case management decisions of the Court. Accordingly, the Court repeats its reasoning in paragraphs 27 to 59 of this Order and dismisses the application.

Application for a waiver of fees for the Three Applications of 11 September 2016

77. As mentioned in paragraph 17 of this Order, the Court is aware that the Appellant’s method of applications by way of letter is unorthodox.

78. At the Hearing, the Court did not make any order on the payment of fees by the Appellant.

79. The Court notes that, at the Hearing, the Respondent had urged the Court to deal with the Appellant’s applications by refusing waiver of the fees.[1] However, the Court proceeded to hear all the applications made by the Appellant. Despite the Respondent’s initial call for the Court to reject the applications because of the non-payment of fees, the Respondent continued to take the Court through the Appellant’s various applications.

80. In light of the Appellant’s circumstances, the Court will reserve the question of whether the fees are payable and make a decision at a later date.

81. On the issue of funds available to the Appellant, the Court notes that funds from the Pro Bono Account have been allocated to the Appellant. In paragraph 2 of the Order of the Chief Justice, it was ordered that amounts up to AED 130,000 in the aggregate would be released from the Pro Bono Account to a legal representative appointed by the Appellant for the purpose of arguing the appeals. Despite the financial assistance extended by the Court, the Appellant failed to take advantage of this offer of legal aid and failed to comply with the deadline given to file his skeleton arguments. The Appellant had disingenuously and repeatedly complained about his inability to access the frozen funds and the Court’s refusal to waive filing fees when the Court went out of its way to structure the hearing of the Three Appeals with the Releasing Fund Appeal first, coupled with the offer of legal aid to put him with certain amounts of funds to mount the first step of his legal battles, which, if successful, might then have put him in sufficient funds to furnish his two other Appeals.

Application to stay or strike out the Claim

82. Any stay application is not applicable as the Immediate Judgment Application has been granted. There are no further proceedings in relation to this part of the legal process which the Appellant may seek to stay.

83. The Appellant cited three reasons why the Claim should be stayed or struck out. First, the Claim should be stayed until the United Nations has issued an opinion regarding the terms of his detention. Second, the Claim should be stayed or struck out pending the resolution of the Appellant’s civil claim against the Respondent in the Dubai Courts. Third, the Appellant requested for a referral of the decision to the judicial tribunal for the DIFC Courts and the Dubai Courts, and then requested for a stay of the Claim pending the decision of the judicial tribunal.

84. With regard to the opinion from the United Nations on the Appellant’s detention, the Court emphasises that the circumstances of the Appellant’s detention are not related to the civil proceedings in the DIFC Courts.

85. In relation to the Appellant’s request to stay or strike out the Claim pending the resolution of his civil claim against the Respondent commenced in the Dubai Courts, the Respondent clarified at the Hearing that there was no civil claim. The Respondent informed the court that the civil case was not ongoing, and was settled at the same time as the criminal proceedings in Dubai. Accordingly, the Appellant’s request to stay or strike out the Claim is dismissed. The transcript of the Hearing stated as follows.

“MR BODNAR:  Yes.  The civil claim in the Dubai Court, there is not a civil claim, as such.  I am sure that you are aware —

CHIEF JUSTICE HWANG:  I am not aware.

MR BODNAR:  The Dubai criminal system is a civil law system, something akin to French Continental and it is possible to engage in the process as a civil party.

CHIEF JUSTICE HWANG:  Sort of a restitutionary claim.

MR BODNAR:  Yes.

CHIEF JUSTICE HWANG:  So it is an adjunct to a criminal proceeding.

MR BODNAR:  It is part, it is integral to it.  In common law jurisdictions a criminal trial is held in front of a jury and it is very separate from a civil claim and the victim is no more and no less in a criminal trial.  In a civil law jurisdiction it is often the case that it is possible for the victim to also be a party to a civil claim to be heard at the same time as the prosecution, because the trial is in front of a professional judge.

CHIEF JUSTICE HWANG:  That is your short answer to —

MR BODNAR:  Yes, but the —

CHIEF JUSTICE HWANG:  Is there a long answer?

MR BODNAR:  Not entirely.  As I understand it, it is a nominal claim.

A MEMBER OF THE BENCH:  May I ask, the civil case here consider as a compensation case, not to claim the (Overspeaking)

MR BODNAR:  Exactly.  Yes.  Exactly.

CHIEF JUSTICE HWANG:  Is that still ongoing?

MR BODNAR:  No.

CHIEF JUSTICE HWANG:  It was settled at the same time as the conviction?

MR BODNAR:  The criminal proceedings have come to an end.  Yes.

CHIEF JUSTICE HWANG:  He was convicted of embezzlement, as you said, and what was the financial order made?

MR BODNAR:  I do not actually know the answer to that question.  I am sure we can find out but, as I understand it, it is a nominal amount.  It was only a nominal amount so that he had some standing in the proceedings.  Because the primary source of recovery is (Inaudible), and there is a good reason for that and is as follows.  The Dubai legal system does not really recognise the concept of a proprietary claim, equitable interests and so on, and civil law does not recognise this (Several inaudible words) inherent in common law.

CHIEF JUSTICE HWANG:  There is some provision in the civil court for restitution (Overspeaking)

MR BODNAR:  (Overspeaking) yes.

CHIEF JUSTICE HWANG:  Not to the same extent as in common law probably.  Yes, go on.

MR BODNAR:  Also the Dubai process is very different to the British process.

CHIEF JUSTICE HWANG:  No, but the main thing is this: do you have two conflicting things going on?

MR BODNAR:  No.

CHIEF JUSTICE HWANG:  Because it is concluded.”

(emphasis added)

86. The Appellant also requested a referral to the judicial tribunal for the DIFC Courts and the Dubai Courts. In the same request, the Appellant requested that the DIFC Courts stay the Claim pending the referral and decision of the judicial tribunal. As the Appellant did not provide any further information in his request, the Court presumes that the Appellant was referring to an application under Decree No. 19 of 2016 in respect of the Judicial Committee at Dubai Courts and at the DIFC Courts (the “Decree”). Article 4 of the Decree provides the application process for a referral of the dispute to the Judicial Committee.

Referral of the dispute to the Joint Judicial Committee

In the event of a conflict of jurisdiction between the Dubai Courts and the Center’s Courts, where neither court did not give up considering the case or both abandoned considering the case or judged a conflicting judgment, the following must be applied:

1.Submit an application to the Judicial Committee through a petition by any of opponents or the Attorney General to identify the competent court or the enforceable judgment.

2. The petition shall be enclosed with a true copy of the statements of claim or applications or conflicting judgments, as applicable.

3. Judicial Committee adjudicates applications submitted as per provided for in this decree in accordance with the legislation(s) in force and the rules of jurisdiction applicable in this regard.”

87. By simply making a request in his Application to the DIFC Courts, the Appellant has not fulfilled the requisite steps for an application to the Joint Judicial Committee. An application should therefore be made directly to the Joint Judicial Committee. The DIFC Courts are inappropriate forums to make such an application. Accordingly, the Court disregards this referral request.

Application to release frozen funds to appoint lawyers and counsel

88. In the Order of the Registrar, it was ordered that the Appellant’s Releasing Funds Appeal was struck out as he failed to file his skeleton arguments by the stipulated deadlines.

89. In the Registrar’s Letter of 20 September 2016, the Registrar informed the Appellant that the Releasing Funds Appeal remained struck out.

90. It is important to note that, while the Releasing Funds Appeal had been struck out, it does not mean that the Appellant is forever denied any use of the frozen funds. An application for the release of any part of the frozen funds must be judged on its own particular merits and therefore each decision on any such application must be fact specific and in light of prevailing circumstances at the time of each application.

91. The Appellant may therefore file a fresh application for a release of funds if he believes he has the justification for doing so, based on his current needs and circumstances. This observation merely states the legal position and is not to be taken as a pre-judgment on the success or otherwise of any such application.

92. The Court also notes that the Appellant sought an order releasing funds to enable the Appellant to file a criminal and civil complaint against the “Dubai-based party” which represented that they would act for the Appellant in defending the Immediate Judgment Application and to which funds of GBP 30,000 were released by the DIFC Court. The Appellant alleged that the “Dubai-based party” had absconded with the funds. The Appellant did not provide any evidence that any funds had been absconded; neither did he identify the “Dubai-based party” he was referring to.

93. As far as the Court is aware, in the Order of Justice Sir David Steel dated 14 May 2015, £40,000 was released to the Appellant for the purpose of dealing with the Respondent’s Immediate Judgment Application. In the same Order, AED 35,000 was released to Nasser Malalla towards the representation of the Appellant in his criminal proceedings. The Court of Appeal is not the appropriate forum to file a claim for the release of funds for an action which has not been commenced in any DIFC Court. An application should be made to the Court of First Instance with regard to any criminal or civil complaint against the “Dubai-based party”.

Application to investigate the alleged “maladministration” by the Registrar and Ms Lema Hatim of the DIFC Court

94. The Appellant alleged that there was maladministration and bungling of the Registrar and Ms Hatim due to a typographical error in an email from the Court which confirmed an extension of the deadline for the filing of the Appellant’s skeleton argument.

95. On 5 September 2016, the Registry sent an email to the Parties to extend the deadline to 14 September 2016.

96. On 8 September 2016, the Registry clarified that there was a typographical error and that the Registry intended to extend the deadline to 7 September 2016 instead of 14 September 2016. Nevertheless, the Registry stated that the deadline of 14 September 2016 would remain, as the Parties were likely to have acted on that basis.

97. In the Appellant’s Application to the DIFC Court, the Appellant submitted that it was “wholly confusing as to what is to be filed and when and whether or not the Judicial authority as opposed to an administrator has approved these changes”.

98. The Appellant further alleged that Ms Hatim mishandled the matter, and wanted to commence an investigation. He stated that she made “several serious mistakes on dates for applications and emails” amongst other instances.

99. Other examples of the alleged maladministration include a breach of Dubai law and procedure as well as the misplacement of “countless letters and applications.”

100. It is not clear how there was any injustice to the Appellant as he was afforded the extended deadline of 14 September 2016. As mentioned in paragraphs 32 to 33 of this Order, the Appellant was given ample opportunities to file his skeleton argument, but still failed to do so without submitting any reason for such failure.

101. Moreover, the Court has taken into account the Appellant’s circumstances by accepting documents submitted by Keystone Law, which was not the Appellant’s counsel on record.

102. The Court takes the view that this is an administrative matter, and not one of judicial or legal application. The Court disagrees with the Appellant that he has any legal justification for asking the Court to direct Ms Hatim to be removed from the performance of her normal duties, which include dealing with the Appellant’s case.

103. Accordingly, the Court dismisses the Appellant’s application.

Costs

104. The Court has not heard submissions for costs from both Parties. Costs will be reserved for Parties to make such submissions within 14 days of this Order.

The post CFI 020/2014 GFH Capital Limited v David Lawrence Haigh appeared first on DIFC Courts.

Hagen v Hannie [2017] SCT 021

$
0
0

Claim No. SCT 021/2017 

THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS

 

In the name of His Highness Sheikh Mohammed Bin Rashid Al Maktoum,

Ruler of Dubai 

IN THE SMALL CLAIMS TRIBUNAL OF DIFC COURTS

BEFORE SCT JUDGE NASSIR AL NASSER

BETWEEN

HAGEN

 Claimant 

and 

HANNIE

Defendant

Hearing:                      16 February 2017

Final submission:        21 February 2017

Judgment:                   28 February 2017


JUDGMENT OF SCT JUDGE NASSIR AL NASSER


UPON hearing the Claimant and the Defendant

AND UPON reading the submissions and evidence filed and recorded on the Court file

IT IS HEREBY ORDERED THAT:

1.The Defendant shall pay the Claimant the sum of AED 12,900 as payment for legal services.

2. The Defendant shall also pay interest on the awarded amount at the rate of 1% over the three months Emirates Interbank Offer Rate (“EIBOR”) per annum from 31 January 2016 to the date of payment.

3. The Defendant shall pay the Claimant the Court fee in the sum of AED 644.96.

4. All other claims shall be dismissed.

 

Issued by:

Nassir Al Nasser

SCT Judge

Date of issue: 28 February 2017

At: 12pm 

 

THE REASONS

The Parties

1.The Claimant is Hagen, an international law firm with a registered office in the DIFC (“the Claimant”).

2. The Defendant is Hannie, an individual formerly working in the DIFC (“the Defendant”).

 Background and the Preceding History

3. On 25 July 2016, the Defendant discussed with the Claimant, by telephone, potential proceedings against the Defendant’s employer. On the same day, following the phone call, the Defendant sent an email to the Claimant with the details of his employer to run a conflict check and detailed some of the issues related to his employment. The Defendant also forwarded his resignation letter and his employment contract to the Claimant. That same day, the Claimant requested additional paperwork related to the issues raised by the Defendant in his discussion with the Claimant.

4. On 26 July 2016, after a meeting held between the parties at the Claimant’s office, the Claimant sent the Defendant a proposal via email regarding its scope of work and professional fees for assisting the Defendant with his dispute with his employer. The email included a summary which reads: “if you are agreeable to the above, please can you let me know so that I can send you our engagement letter”.

5. On 27 July 2016, the Defendant responded to the Claimant’s email stating the following: “request you to please go ahead and prepare the engagement letter. I shall be in your office tomorrow morning around 10:30am for meeting to discuss questions and the strategy going forward”.

6. At 8:54am on 28 July 2016, shortly prior to the meeting scheduled between the parties, the Defendant sent the Claimant an email with additional concerns and queries related to their meeting that same day. The concerns related to the dispute between the Defendant and his employer and the Defendant included a query in regards to the fee structure between the Claimant and the Defendant. On the same day, the Defendant also requested that the Claimant refrain from preparing any letters or legal notices to his employer until further instruction and also requested the Claimant to send him a final engagement letter and fee proposal. Later on that same day, the Claimant by email indicated that it had received further documents from the Defendant by email.

7. On 30 July 2016, the Defendant by email referred to the discussions had at the 28 July 2016 meeting, and requested the Claimant to provide the payment schedule which was discussed between the parties.

8. On 31 July 2016, the Claimant sent the Defendant the engagement letter to be reviewed and signed together with the Claimant’s standard terms of business.

9. On 1 August 2016, the Defendant by email acknowledged receipt of the engagement letter and requested time to get back to the Claimant. On the same day, the Claimant via email mentioned to the Defendant that no further work would be undertaken on the matter until he responded and that if the Defendant decided not to proceed, the Claimant would only bill the Defendant for the time spent on the matter to date.

10. The Claimant did not receive any further correspondence from the Defendant until 9 August 2016, at which time the Defendant informed the Claimant that he was still waiting for his employer to file a claim and that he would update the Claimant at a later point.

11. On 10 August 2016, the Claimant sent the Defendant an invoice, Invoice No. 201640261 (“the Invoice”), dated 10 August 2016 for the amount of AED 12,900 for time spent on the Defendant’s matter from 26 July 2016 until 28 July 2016. Since then the Defendant has not responded to any communications from the Claimant although the Defendant sent numerous emails to him from August until October 2016.

12. On 4 January 2017, the Claimant sent the Defendant a legal notice regarding the outstanding Invoice but the Claimant did not receive a response.

13. On 31 January 2017, the Claimant filed a claim in the Small Claim Tribunal of the DIFC Courts (the “SCT”) claiming the sum of USD $ 3,510 (equivalent to AED 12,900) as per the Invoice sent to the Defendant on 10 August 2016.

Particulars and Defence

14. The Claimant’s argument is that the core terms of the contract between it, an international law firm, and the Defendant, its client, are agreed in the scope of work and the fee structure provided by the firm to the client. These terms essentially provide that the legal advisors will charge the client for the time spent on the matter. These are the terms upon which a lawyer’s proposal to a potential client are accepted or rejected.

15. The Claimant’s argument continues that the email sent by it to the Defendant on 26 July 2016 was an offer to contract, including the intended scope of work and the professional fees required. The Claimant indicates at the end of the email that if the Defendant agrees to the above (scope of work and professional fees), he should respond affirmatively to the email. Thereafter, on 27 July 2016, the Defendant responded by email, stating that he “request[s] [the Claimant] to please go ahead and prepare the engagement letter” and “I shall be in your office tomorrow morning for meeting to discuss questions and the strategy going forward”. Therefore, the Claimant argues, the parties created a valid and binding contract via an offer and an acceptance sent by email.

16. On the other hand, the Defendant argues that from 25 July 2016 there was no mention of charges for the time spent on his matter. The Defendant also added that he did not use the word “I agree” in his reply to the Claimant’s offer, although he did request the Claimant to go ahead and draft the engagement letter. This request, he argues, was not an acceptance of the terms provided in the offer email.

17. On 28 July 2016, prior to the 10:30am meeting scheduled between the parties, the Defendant argues that he provided a list of questions related to the Disgorgement Claim, Visa Cancellation and the fee structure, implying that the parties were not yet in agreement on the terms of engagement. The Defendant conceded at the Hearing that the Claimant answered all questions raised by the Defendant at the meeting held on 28 July 2016.

18. The Claimant responded that the majority of these questions addressed on 28 July 2016 were considered legal advice given to the Defendant and any discussion regarding the fee structure was minor. The only amendment made to the fee structure based on the Defendant’s requests of 28 July 2016 was to add stages to the scope of work and to cap the fee in each stage.

19. The Defendant also argues that the Claimant’s charges reflected in the Invoice are not valid due to the fact that the Defendant mentioned to the Claimant that he was unable to pay the AED 10,000 required deposit (money on account). The Defendant argues that the Claimant assured him that the initial meetings held would not be chargeable until the engagement letter was signed. However, the Claimant argues that the terms used (“no payment will be necessary before the meeting”) was with reference to a waiver of the AED 10,000 deposit which the Defendant said that he would not be able to pay and which is generally required from a client before further legal work is performed.

Findings

20. The DIFC Courts and the Small Claims Tribunal have jurisdiction over this dispute as it concerns matters occurring within the DIFC and the amount in question does not exceed AED 500,000.

21. This dispute is governed by DIFC Law No. 6 of 2004 (the “DIFC Contract Law”), as stated in Article 3:

“Application of the Law

This Law applies in the jurisdiction of the Dubai International Financial Centre.”

22. Pursuant to Article 15 of DIFC Contract Law, a valid offer to contract is defined as follows:

“A proposal for concluding a contract constitutes an offer if it is sufficiently definite and indicates the intention of the offeror to be bound in case of any acceptance”.  

23. The question is whether the Claimant’s email of 26 July 2016 constitutes a valid offer to contract pursuant to Article 15 of the DIFC Contract Law and if so, whether that offer was accepted by the Defendant’s email response of 27 July 2016. The Claimant’s email clearly and expressly states that “if you are agreeable to the above, please can you let me know so that I can send you our engagement letter”. The Defendant, in his response on 27 July 2016, states that he “request[s] you to please go ahead and prepare the engagement letter. I shall be in your office tomorrow morning around 10:30 am for a meeting to discuss questions and the strategy”.

24. Upon reviewing the correspondence between the parties, I have reached the conclusion that a valid offer to contract was presented by the Claimant by way of email on 26 July 2016. The Defendant, in his email response of 27 July 2016, accepted the Claimant’s offer although no formal contract was signed between the parties.

25. Article 24(1) of DIFC Contract Law states the following:

“A reply to an offer which purports to be an acceptance but contains additions, limitations or other modifications is a rejection of the offer and constitutes a counter-offer”.

26. The Defendant argued that there were additions and modifications made to the terms of the engagement letter drafted by the Claimant due to discussions at the meeting held between the parties on 28 July 2016 such that he provided a counter-offer rather than accepting the Claimant’s initial offer. He added that the meeting resulted in the following modifications and additions:

a. the scope of work was split into different stages;

b. additional points were added to the scope of work;

c. legal fees were capped for each stage of the scope of work;

d. standard terms of business of Claimant were sent together with the engagement letter; and

e. payment on account was increased from AED 10,000 to AED 15,000.

27. The Defendant also argued that the Claimant on 27 October 2016 confirmed the modifications listed above, and that the Claimant stated the following “We sent you our engagement letter on 1 August 2016 which mirrored our initial proposal but as requested set out the capped fees for each stage”.

28. On the other hand, the Claimant argued that the Defendant has misunderstood Article 24(1) of DIFC Contract Law and that the article would apply if the Defendant had replied to the proposal requesting a substantive change made to the terms, which the Claimant argues did not happen. Furthermore, the Claimant added that the Defendant was not silent or inactive regarding acceptance; he indicated his assent and confirmed his acceptance to the proposal provided to him by the Claimant. The Claimant also added that the Defendant requested meetings, asked questions, and accepted legal advice and the Defendant was far from silent or inactive with regards to retaining the services of the Claimant.

29. I have examined the evidence provided by both parties and, as mentioned above, I am of the view that the parties entered into a valid and binding contract. However, the parties made a subsequent agreement for minor changes to be made at the meeting held on 28 July 2016; the Defendant’s requested changes did not amount to a counter-offer. Therefore, the engagement letter mirrored the initial proposal made by the Claimant on 26 July 2016 and the changes included were amendments agreed by both parties at the meeting held on 28 July 2016.

30. Furthermore, had the Defendant been silent or inactive, his conduct towards the Claimant by arranging meetings and presenting documents to be reviewed would qualify as an acceptance by conduct pursuant to Article 19(1) of the DIFC Contract Law, which states the following:

“A statement made by or other conduct of the offeree indicating assent to an offer is an acceptance. Silence or inactivity does not in itself amount to acceptance.”

31. The Defendant argued that the Claimant misrepresented the Defendant’s silence as an acceptance to the proposal. However, the Claimant argues that the Defendant accepted in writing, via email, the initial proposal and that he also provided the Claimant with documents related to his dispute, requested meetings, and discussed legal questions with the Claimant.

32. The Defendant was not silent with regards to the initial proposal as he not only indicated his assent to the offer via his conduct, but accepted the offer in writing via his email sent on 27 July 2016. While the Defendant remained silent once the engagement letter was sent to him, the engagement letter was merely a reflection of what was already agreed upon in the initial offer with some amendments made upon both parties’ agreement. In addition, the Defendant’s conduct during the period between 26 July 2016 and 28 July 2016 indicates his clear acceptance of the Claimant’s offer to provide him with legal services.

33. The Defendant argues that one of the fundamental principles of contract law is that there must be a “common intention” between two parties before the contract is considered valid and enforceable. The Defendant continues that, pursuant to Article 51(a) of the DIFC Contract Law, preliminary negotiation between the parties is a key consideration when ascertaining the content of the common intention between the parties. He also argues that, given the modifications made to the engagement letter, it must be concluded that the common intention between the parties was still under preliminary negotiations and that there was therefore no valid and enforceable contract made between the parties. However, the Claimant responded that clear and valid offer and acceptance had occurred between the parties and the Claimant had performed its obligation in accordance with the agreement. The Claimant argued that the relationship was clearly beyond “preliminary negotiations”.

34. I have read the case file, examined the evidence provided and heard the parties at the Hearing and I have concluded that the parties were not in a negotiation stage, but in fact the Claimant had already begun carrying out the scope of work agreed between the parties. The amendments made to the agreement do not suggest that the parties were in negotiation stage; the conduct of both parties was beyond “preliminary negotiations”.

35. The Defendant argues that the terms set out in the proposal qualify as “unclear” because they did not mention the standard terms of business, a full description of the scope of work and the modified fee structure. Therefore, pursuant to Article 54 of the DIFC Contract Law, which states that “If contract terms supplied by one party are unclear, an interpretation against that party is preferred,” the Defendant argues that the Claimant is not owed payment. However, the Claimant denies that the term of the contract are unclear. Furthermore, the Claimant argues that the Defendant did not request a clarification or any substantive amendments, indicating that the terms were clear.

36. I find that the parties agreed to the proposal and neither raised any concerns that the agreement was unclear. The only comment the Defendant had is the one in relation to the deposit amount on account which was waived by the Claimant and the fee structure was capped. Therefore, I disagree that the contract between the parties was unclear.

37. In conclusion, the parties did enter into an agreement on 27 July 2016 the moment the Defendant responded to the Claimant’s offer reflected in the email sent on 26 July 2016. Although there were minor amendments agreed between the parties on 28 July 2016 as mentioned above, those amendments did not significantly affect the substance of the proposal. Even if the Defendant’s response was not an acceptance, the conduct of the Defendant amounted to an acceptance of the Claimant’s offer as the Defendant’s intended acceptance was clear from his requests for legal advice and his scheduling meetings with the Claimant.

38. For the reasons stated above, the Defendant shall pay the Claimant the sum of AED 12,900 pursuant to the Invoice presented by the Claimant for its performance of legal work from 26 July 2016 to 28 July 2016. The Defendant shall also pay interest on the awarded amount at the rate of 1% over the three months Emirates Interbank Offer Rate (“EIBOR”) per annum from 31 January 2016 to the date of payment. The Defendant shall also be responsible to reimburse the Claimant for the DIFC Courts’ fee in the amount of AED 644.96.

39. There was no evidence that the Claimant suffered loss and damages. Therefore, I dismiss the Claimant’s claim for loss and damages.

 

Issued by:

Nassir Al Nasser

SCT Judge

Date of Issue: 28 February 2017

At: 12pm

The post Hagen v Hannie [2017] SCT 021 appeared first on DIFC Courts.

Viewing all 1139 articles
Browse latest View live